Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 21,837 200.96 0.92  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Formal work order for Laying of UPVC distribution pipeline and Providing FHTC (Functional Household Tap Connection) for Augmentation of Dakshin Chatra Zone-II Water Supply Scheme in Swarupnagar Block of North 24 Parganas District under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001186/2022-2023 1041/BD 31/03/2023 90 DIAMOND ENGINEER'S CO-OP. SOCIETY LTD. 378.49 196.92 52.03 37
2 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Route Survey, Design Drawing & DPR Preparation for Dakshin Chatra Zone II Water Supply Scheme in Swarupnagar Block under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/002754/2021-2022 442/ BHTSD 22/03/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.04 4.04 100 1
3 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Material Requisition To Resource Division RTOR000017/2023-2024 1239/BD 25/04/2023 Resource Division 69.20 0.00 0 0
4 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Material Requisition To Resource Division RTOR000064/2023-2024 1627/BD 01/06/2023 Resource Division 19.43 0.00 0 0
5 NORTH 24 PARAGANAS Central Drilling Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 300 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
6 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Dakshin Chatra Zone II to accommodate FHTC , SM/11658 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No II (Rep.) (Zone-I and II) under Dakshin Chatra W/S Scheme District of 24 Pgs. (N) ORD/001911/2023-2024 6734/EMD 29/11/2023 30 CONCORD ENGINEERING 26.08 0.00 0 0
Total 21,836.99 200.96 0.92