Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
5 | 461.28 | 106.01 | 22.98 | ||||||||||||||
1 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Patua to accommodate FHTC , SM/11656 | Augmentation | Formal work order for Laying of DI/UPVC distribution pipe line and Providing Functional House Hold Tap Connection (FHTC) for Augmentation of Patua Water Supply Scheme in Swarupnagar Block of North 24 Parganas District under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000787/2022-2023 | 3549/BD | 06/12/2022 | 90 | SUBHASH BOSE. | 326.66 | 101.85 | 31.18 | 27 | |
2 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Patua to accommodate FHTC , SM/11656 | Augmentation | Route Survey, Design Drawing & DPR Preparation for Patua Water Supply Scheme in Swarupnagar Block under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/002755/2021-2022 | 444/ BHTSD | 22/03/2022 | 15 | SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. | 4.16 | 4.16 | 100 | 1 | |
3 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Patua to accommodate FHTC , SM/11656 | Augmentation | Material Requisition To Resource Division | RTOR000180/2022-2023 | 601/BD | 23/02/2023 | Resource Division | 6.94 | 0.00 | 0 | 0 | ||||
4 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Patua to accommodate FHTC , SM/11656 | Augmentation | Material Requisition To Resource Division | RTOR000201/2022-2023 | 859/BD | 20/03/2023 | Resource Division | 48.85 | 0.00 | 0 | 0 | ||||
5 | NORTH 24 PARAGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Patua to accommodate FHTC , SM/11656 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I and II (Replacement) under Bharatpur W/S Scheme, Patua W/S Scheme (P/H-I & II) & Chaital W/S Scheme (P/H -I & II) District of 24 Pgs. (N). NIET No. 24 of EE/EMD of 2022-23 (Sl. No.- 04) | ORD/000824/2022-2023 | 31/EMD | 03/01/2023 | 30 | M/S P.P. ELECTRICALS | 74.67 | 0.00 | 0 | 0 | |||
Total | 461.30 | 106.01 | 22.98 |