Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 473.2 418.66 88.47  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Sadik Nagar Zone-I water supply scheme in Basirhat-II Block under Barasat Division, P.H.E Dte. Assistant Engineer Junior Engineer ORD/000825/2022-2023 3605/BD 09/12/2022 90 PUSPA ENTERPRISE. 406.99 391.67 96.24 100
2 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Route Survey, Design Drawing & DPR Preparation for SADIKNAGAR-I Water Supply Scheme in Basirhat-II Block under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/002782/2021-2022 206/ BHTSD 28/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.15 3.96 95.42 1
3 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Material Requisition To Resource Division RTOR000139/2022-2023 3816/BD 23/12/2022 Resource Division 17.46 0.00 0 0
4 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Material Requisition To Resource Division RTOR000158/2023-2024 4404/BD 10/11/2023 Resource Division 18.48 0.00 0 0
5 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.II (Zone-I) (Replacement) under Sadiknagar W/S Scheme District of 24 Pgs. (N). (SM/11525) NIET No.- 19 of EE/EMD of 2022-23 (Sl. No.- 24) ORD/000583/2022-2023 6396/EMD 24/11/2022 30 S.S.ENTERPRISES 13.04 11.50 88.19 0
6 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Sadiknagar (Zone-I) to accommodate FHTC , SM/11525 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I (Zone-I) (Replacement) under Sadiknagar W/S Scheme District of 24 Pgs. (N). (SM/11525) NIET No.- 19 of EE/EMD of 2022-23 (Sl. No.- 26) ORD/000584/2022-2023 6397/EMD 24/11/2022 30 ESENCE ENGINEERING CONCERN 13.08 11.53 88.15 0
Total 473.19 418.66 88.48