Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
13 | 670.78 | 415.06 | 61.88 | ||||||||||||||
1 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Acceptance cum work order for Sinking of 1 no. 250 mm. x 150 mm. dia. 270 mtr deep tubewell by D.R. Rig method having 250 mm. dia. 36 mtr. long housing pipe & 150 mm. dia. 30 mtr. long Filter at Head Work Site of Maslandapur water supply scheme (Zone - II) within the jurisdiction of Habra Sub-Division, under Barasat Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000044/2023-2024 | 1406/BD | 08/05/2023 | 30 | ARUN TRADERS | 14.49 | 6.71 | 46.31 | 100 | |
2 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Acceptance cum work order for Construction of the Boundary wall in Pump House No. 2 of Maslandapur- II Piped Water Supply Scheme in connection with Augmentation work under JJM project within the jurisdiction of Habra Sub-Division under Barasat Division, PHE Dte. | Assistant Engineer | ORD/000355/2024-2025 | 2410/BD | 22/08/2024 | 35 | M/S MITRA CONSTRUCTION | 5.71 | 0.00 | 0 | 0 | ||
3 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Acceptance cum work order for Construction of the Boundary wall in Pump House No. 3 of Maslandapur- II Piped Water Supply Scheme in connection with Augmentation work under JJM project within the jurisdiction of Habra Sub-Division under Barasat Division, PHE Dte. | Assistant Engineer | ORD/000356/2024-2025 | 2409/BD | 22/08/2024 | 45 | JOY ENTERPRISE | 6.10 | 0.00 | 0 | 0 | ||
4 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Formal Work order for Providing Functional House Hold Tap Connection (FHTC) from existing and new proposed distribution system for Augmentation of Maslandapur Water Supply Scheme (Zone - II) within the jurisdiction of Habra Sub-Division under Barasat Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000534/2022-2023 | 2448/BD | 23/08/2022 | 90 | ALOK ENTERPRSE. (A UNIT OF SAKET TREXIM PVT.LTD) | 526.45 | 381.78 | 72.52 | 1 | |
5 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Improvement of Iron Elimination Plant at Maslandapur Zone II WS Scheme within the jurisdiction of Habra Sub-Division under Barasat Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/001406/2023-2024 | 671/HAB | 30/10/2023 | 30 | S.G. ENTERPRISE | 4.47 | 2.21 | 49.44 | 100 | |
6 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Acceptance cum work order for Sinking of 1 no. 300 mm. x 200 mm. dia. 270 mtr deep tubewell by D.R. Rig method having 300 mm. dia. 36 mtr. long housing pipe & 200 mm. dia. 30 mtr. long Filter at Pump House No. - 2 of Maslandapur(Zone - II) water supply scheme within the jurisdiction of Habra Sub-Division, under Barasat Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/001533/2023-2024 | 07/BD | 02/01/2024 | 30 | M/S B.K.ENTERPRISE. | 19.45 | 8.35 | 42.93 | 100 | |
7 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Construction of Service Road (10 Mtr. Length & 2 Mtr. Wide while 1.00 Mtr existing Road ) for Pump House No:2 of Maslandapur II Piped Water Supply Scheme in connection with Augmentation work under JJM project within the jurisdiction of Habra Sub-Division under Barasat Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/001886/2023-2024 | 134/HAB | 05/02/2024 | 15 | CHAKRABORTY SUPPLIERS & CONSTRUCTION. | 0.75 | 0.37 | 49.33 | 0 | |
8 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Construction of Service Road (10 Mtr. Length & 2 Mtr. Width) for Pump House No:3 of Maslandapur II Piped Water Supply Scheme in connection with Augmentation work under JJM project within the jurisdiction of Habra Sub-Division under Barasat Division, PHE Dte. | ORD/001887/2023-2024 | 135/HAB | 05/02/2024 | 15 | JOY ENTERPRISE | 0.60 | 0.00 | 0 | 0 | |||
9 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Repairing & renovation of Pump House No. - 1 & 2 of Maslandapur W/S scheme (Zone - II) within the jurisdiction of Habra Sub-Division under Barasat Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/002977/2021-2022 | 490/HAB | 30/11/2021 | 30 | ANJALI CONSTRUCTION. | 2.18 | 2.17 | 99.54 | 1 | |
10 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Material Requisition To Resource Division | RTOR000042/2022-2023 | 2515/BD | 25/08/2022 | Resource Division | 22.72 | 0.00 | 0 | 0 | ||||
11 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Material Requisition To Resource Division | RTOR000057/2023-2024 | 1558/BD | 23/05/2023 | Resource Division | 1.85 | 0.00 | 0 | 0 | ||||
12 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Material Requisition To Resource Division | RTOR000124/2022-2023 | 3790/BD | 22/12/2022 | Resource Division | 34.22 | 0.00 | 0 | 0 | ||||
13 | NORTH 24 PARAGANAS | Eastern Mechanical | Augmentation of Ground water based piped water supply scheme for Maslandapur Zone-II to accommodate , SM/10533 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I, II & III (Zone-II) under Maslandapur W/S Scheme (Rep.) District of 24 Pgs. (N) NIET No.- 29 of EE/EMD of 2022-23 (Sl. No.- 27) | Assistant Engineer | Junior Engineer | ORD/001977/2022-2023 | 1321/EMD | 29/03/2023 | 30 | A.K. ENTERPRISE | 31.79 | 13.47 | 42.37 | 80 | |
Total | 670.76 | 415.07 | 61.88 |