Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 559.36 389.2 69.58  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at Pump House No.- 1 & 2 with PVC pipe & strainer having 300mm dia 36 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Kumarjole w/s scheme, Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000372/2022-2023 2437/BD 22/08/2022 30 AUXILIARY TUBE WELL DRILLERS. 44.41 32.03 72.12 100
2 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for Restoration of RCC drain from Joygram Bazar Idgah to near Pintu Molla Garage for damaged portion due to laying of 150 mm dia DI Rising main of Kumarjole w/s scheme, Minakhan block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000528/2022-2023 1238/HSD 20/07/2022 21 JESMINE ENTERPRISE. 4.76 4.67 98.11 1
3 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for Restoration of RCC drain from Pintu Molla Garage to N/H/O Sahidul Molla for damaged portion due to laying of 150 mm dia DI Rising main of Kumarjole w/s scheme, Minakhan block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000529/2022-2023 1240/HSD 20/07/2022 21 JESMINE ENTERPRISE. 4.74 4.67 98.52 1
4 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for Restoration of RCC drain from Near Julfikar Molla shop to N/H/O Sariful Molla for damaged portion due to laying of 150 mm dia DI Rising main of Kumarjole w/s scheme, Minakhan block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000530/2022-2023 1244/HSD 20/07/2022 21 JESMINE ENTERPRISE. 3.39 3.26 96.17 1
5 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for Restoration of RCC drain from N/H/O Sahidul Molla to near Julfikar Molla shop for damaged portion due to laying of 150 mm dia DI Rising main of Kumarjole w/s scheme, Minakhan block under Hasnabad Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000531/2022-2023 1246/HSD 20/07/2022 21 JESMINE ENTERPRISE. 4.76 4.42 92.86 1
6 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Formal work order for Laying of UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Kumarjole water supply scheme, Minakhan Block within Hasnabad Sub-Division, under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000597/2022-2023 2676/BD 08/09/2022 90 JAL PRAVAHIKA PVT. LTD. 260.00 259.94 99.98 1
7 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Formal work order for Construction of 400cum capacity 20mtr staging height R.C.C Over Head Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Kumarjole water supply Scheme, Minakhan Block under Hasnabad Sub-Division PHE Dte. Assistant Engineer Junior Engineer ORD/000755/2023-2024 2612/BD 29/08/2023 365 S.S.ENTERPRISE. (BAMANGACHI) 153.33 70.18 45.77 100
8 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Acceptance cum work order for 2 nos. pump connection at PH No.-1 & 2 in connection with Augmentation of Kumarjole water supply scheme, Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001857/2023-2024 37/HSD 09/01/2024 10 ABDUL ALIM MONDAL. 0.83 0.40 48.19 100
9 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Material Requisition To Resource Division RTOR000040/2022-2023 2472/BD 24/08/2022 Resource Division 8.92 0.00 0 0
10 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of Ground water based piped water supply scheme for Kumarjole , SM/10302 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I & II under Bira-Rajibpur W/S Scheme, Khasdelpur W/S Scheme and Kumarjole W/S Scheme with Pump House No-I under Sadpur W/S Scheme District of 24 Pgs. (N) Assistant Engineer Junior Engineer ORD/002529/2023-2024 4490/EMD 14/07/2023 30 EASTERN INDIA SALES & SERVICE 74.22 9.63 12.97 58
Total 559.35 389.19 69.58