Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 1,491.36 67.29 4.51  
1 PURBA BARDHAMAN Raina - I Burdwan Division BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to BELSHAR & SANKARPUR Piped Water Supply Scheme under Raina ¿ I Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000411/2023-2024 3256/BWD 27/07/2023 365 SK ALIM 1,345.74 55.51 4.12 44
2 PURBA BARDHAMAN Raina - I Burdwan Division BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Material Requisition To Resource Division RTOR000247/2023-2024 2197/BWD 12/05/2023 Resource Division 1.80 0.00 0 0
3 PURBA BARDHAMAN Raina - I Burdwan Division BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Material Requisition To Resource Division RTOR000423/2023-2024 3860/BWD 01/09/2023 Resource Division 3.41 0.00 0 0
4 PURBA BARDHAMAN Raina - I Burdwan Division BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Material Requisition To Resource Division RTOR000654/2023-2024 5100/BWD 23/11/2023 Resource Division 20.46 0.00 0 0
5 PURBA BARDHAMAN Raina - I Central Mechanical BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New New electric connection for Belswar PWSS, PH-1. BILL/01872/2023-2024 BP-2023-24-360 11/01/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 9.01 0.00 0 0
6 PURBA BARDHAMAN Raina - I Central Mechanical BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New NEW SERVICE CONNECTION FOR BELSHAR PWSS TW 2. BILL/03182/2023-2024 BP-2023-24-666 22/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 7.39 0.00 0 0
7 PURBA BARDHAMAN Raina - I Central Mechanical BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Bajitpur, Belsar & other water supply scheme under Raina-1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000117/2024-2025 2589/CMD 27/08/2024 90 DEY ENTERPRISE 74.58 0.00 0 0
8 PURBA BARDHAMAN Raina - I Central Mechanical BELSHAR PIPED WATER SUPPLY SCHEME , SM/18338 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Belshar Water Supply Scheme [ Block- Raina-1 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000719/2023-2024 4030/CMD 29/08/2023 30 SINHA ELECTRICALS 28.97 11.78 40.66 0
Total 1,491.36 67.29 4.51