Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 1,189.41 3.43 0.29  
1 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Continuation work order for "Hiring of one no. DIESEL MOTOR CAB (BS-VI) (Inspection Vehicle) for JJM projects for the Office of the Assistant Engineer, under Kalna Sub-Division within Burdwan Division, P.H.E. Dte. [Period from 01.06.2024 to 30.11.2024]" (Vehicle No-WB 04G 7127) Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000465/2024-2025 272/KSD 30/05/2024 183 PARTHA PRATIM ACHARYA 2.40 1.22 50.83 0
2 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to ANGARSON, BHABANANDAPUR &DAFARPUR Piped Water Supply Scheme under Kalna ¿ II Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE,Junior Engineer, R.W.S. Burdwan Sub Division, P.H.E. Dt ORD/000702/2023-2024 4480/BWD 11/10/2023 365 M/S GHOSH & CO. 1,093.29 0.00 0 35
3 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Work Order for "Hiring of one no. DIESEL MOTOR CAB (BS-VI) (Inspection vehicle) for JJM projects for the Office of the Assistant Engineer, under Kalna Sub-Division within Burdwan Division, P.H.E. Dte. [Period from 01.12.2023 to 31.05.2024]" (Vehicle No-WB 04G 7127) Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/000983/2023-2024 1681/KSD 22/11/2023 183 PARTHA PRATIM ACHARYA 0.87 1.24 142.53 51
4 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Work Order for "CONSTRUCTION OF TEMPORARY KIOSK FOR THE NECESSARY ARRANGEMENT OF ELECTRIFICATION OF TUBEWELL FOR DAFARPUR PWSS UNDER KALNA SUB-DIVISION UNDER BURDWAN DIVISION, PHE DTE." Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/001148/2023-2024 2104/KSD 04/03/2024 10 ER CONSTRUCTION & GENERAL ORDER SUPPLIER 0.66 0.66 100 2
5 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Work Order for "Hiring of one no. DIESEL MOTOR CAB (BS-VI) (Inspection vehicle) for JJM projects for the Office of the Assistant Engineer, under Kalna Sub-Division within Burdwan Division, P.H.E. Dte. [Period from 01.12.2023 to 31.05.2024]" (Vehicle No-WB 04G 7127) Assistant Engineer JUNIOR ENGINEER KALNA SUB-DIVISION PHE DTE ORD/001248/2023-2024 1681/KSD 22/11/2023 183 PARTHA PRATIM ACHARYA 2.40 0.31 12.92 0
6 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Material Requisition To Resource Division RTOR000075/2023-2024 1962/BWD 25/04/2023 Resource Division 28.10 0.00 0 0
7 PURBA BARDHAMAN Kalna - II Burdwan Division DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Material Requisition To Resource Division RTOR000237/2023-2024 2197/BWD 12/05/2023 Resource Division 12.02 0.00 0 0
8 PURBA BARDHAMAN Kalna - II Central Mechanical DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Additional quotation for Dafarpur PWSS PH-2 BILL/00426/2024-2025 BP-2024-25-224 26/07/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.51 0.00 0 0
9 PURBA BARDHAMAN Kalna - II Central Mechanical DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New New service at Dafarpur PWSS TW-2. BILL/02292/2023-2024 BP-2023-24-438 29/01/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 4.70 0.00 0 0
10 PURBA BARDHAMAN Kalna - II Central Mechanical DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New NEW SERVICE CONNECTION FOR DAFARPUR PWSS TW -1. BILL/03103/2023-2024 BP-2023-24-643 15/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 20.65 0.00 0 0
11 PURBA BARDHAMAN Kalna - II Central Mechanical DAFARPUR PIPED WATER SUPPLY SCHEME , SM/16028 New Supply & Installation of Submersible Pumping Machinery , Voltage Stabilizer, Chlorination system and internal House wiring for Tube well no.- 1 & 2 at DAFARPUR Water Supply Scheme [Block - KALNA-2] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ORD/000895/2023-2024 4158/CMD 29/08/2023 30 GOENKA ENTERPRISE 20.81 0.00 0 0
Total 1,189.41 3.43 0.29