Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
5 | 323.52 | 41.52 | 12.83 | ||||||||||||||
1 | PURBA BARDHAMAN | Jamalpur | Burdwan Division | GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15583 | New | GOPALPUR Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Jamalpur Block, District:- Purba-Bardhaman [NEW SCHEME] | AE(HQs) | Junior Engineer, Burdwan Division | ORD/000121/2023-2024 | 2305/BWD | 19/05/2023 | 120 | IJABUL SEKH | 266.75 | 41.52 | 15.57 | 40 |
2 | PURBA BARDHAMAN | Jamalpur | Burdwan Division | GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15583 | New | Material Requisition To Resource Division | RTOR000268/2023-2024 | 2197/BWD | 12/05/2023 | Resource Division | 17.02 | 0.00 | 0 | 0 | |||
3 | PURBA BARDHAMAN | Jamalpur | Central Mechanical | GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15583 | New | New service connection for Gopalpur PWSS TW-1. | BILL/02282/2023-2024 | BP-2023-24-433 | 29/01/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 4.00 | 0.00 | 0 | 0 | |||
4 | PURBA BARDHAMAN | Jamalpur | Central Mechanical | GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15583 | New | New Service connection at GOPALPUR PWSS TW-2. | BILL/02363/2023-2024 | BP-2023-24-483 | 31/01/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 13.65 | 0.00 | 0 | 0 | |||
5 | PURBA BARDHAMAN | Jamalpur | Central Mechanical | GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15583 | New | Supply & Installation of Submersible Pumping Machinery , Voltage Stabilizer, Chlorination System and Internal House wiring for Tube well no.- 1 & 2 at GOPALPUR Water Supply Scheme [Block-JAMALPUR] under CMD, PHE Dte., Dist.- Purba-Bardhaman. | ASSISTANT ENGINEER | JUNIOR ENGINEER | ORD/000904/2023-2024 | 4168/CMD | 29/08/2023 | 30 | SOUNAK ENTERPRISE | 22.10 | 0.00 | 0 | 0 |
Total | 323.52 | 41.52 | 12.83 |