Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 379.94 72.25 19.02  
1 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF BERWA PIPED WATER SUPPLY SCHEME , SM/15568 Augmentation Replacement of Tube-well & Rising main at Head work TW site for BARWA Piped Water Supply Scheme under MEMARI-II Block, District:- Purba-Bardhaman. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER RWS BURDWAN SUB-DIVISION PHE DTE ORD/000226/2024-2025 2523/BWD 03/07/2024 90 ROY ENTERPRISE 15.27 6.07 39.75 80
2 PURBA BARDHAMAN Burdwan Division AUGMENTATION OF BERWA PIPED WATER SUPPLY SCHEME , SM/15568 Augmentation Augmentation of BERWA Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 150 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Memari-II Block, District:- Purba-Bardhaman. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER RWS BURDWAN SUB-DIVISION PHE DTE ORD/000587/2023-2024 3743/BWD 28/08/2023 365 ROY ENTERPRISE 334.82 66.18 19.77 35
3 PURBA BARDHAMAN Central Mechanical AUGMENTATION OF BERWA PIPED WATER SUPPLY SCHEME , SM/15568 Augmentation NEW SERVICE CONNECTION FOR AUGMENTATION OF BERWA PIPED WATER SUPPLY SCHEME. BILL/02827/2023-2024 BP-2023-24-594 04/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 7.25 0.00 0 0
4 PURBA BARDHAMAN Central Mechanical AUGMENTATION OF BERWA PIPED WATER SUPPLY SCHEME , SM/15568 Augmentation Supply & Installation of Submersible Pumping Machinery , Voltage Stabilizer, Chlorination system and internal House wiring for Tube well no.- 1&2 at Augumentation of Berawa Water Supply Scheme under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER Junior Engineer ORD/000101/2023-2024 2600/CMD 07/06/2023 30 SOUNAK ENTERPRISE 22.60 0.00 0 0
Total 379.95 72.24 19.01