Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 1,220.87 | 6.63 | 0.54 | ||||||||||||||
1 | PURBA BARDHAMAN | Kalna - I | Burdwan Division | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to TAIPARA & NIRALGACHHI Piped Water Supply Scheme under Manteswar Block, District:- Purba-Bardhaman [NEW SCHEME] | Assistant Engineer | Junior Engineer, R.W.S. Burdwan Sub Division, P.H.E. Dt | ORD/000048/2023-2024 | 1825/BWD | 19/04/2023 | 365 | S. GHOSH & ASSOCIATES PVT LTD. | 1,064.74 | 6.63 | 0.62 | 40 |
2 | PURBA BARDHAMAN | Kalna - I | Burdwan Division | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Material Requisition To Resource Division | RTOR000042/2023-2024 | 1962/BWD | 25/04/2023 | Resource Division | 37.35 | 0.00 | 0 | 0 | |||
3 | PURBA BARDHAMAN | Kalna - I | Burdwan Division | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Material Requisition To Resource Division | RTOR000178/2023-2024 | 2155/BWD | 10/05/2023 | Resource Division | 20.14 | 0.00 | 0 | 0 | |||
4 | PURBA BARDHAMAN | Kalna - I | Central Mechanical | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | NEW SERVICE CONNECTION FOR NIRALGACHI PWSS TW-I | BILL/00106/2024-2025 | BP-2024-25-42 | 26/04/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 9.14 | 0.00 | 0 | 0 | |||
5 | PURBA BARDHAMAN | Kalna - I | Central Mechanical | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Quotation for new service connection at Niralgachi PWSS TW-2. | BILL/00663/2024-2025 | BP-2024-25-265 | 20/08/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 8.28 | 0.00 | 0 | 0 | |||
6 | PURBA BARDHAMAN | Kalna - I | Central Mechanical | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Installation of two tank chlorination system, Yard lighting arrangement & allied works at Joykrishnapur & others water supply scheme under Purbasthali-2,jamalpur,kalna 1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. | ASSISTANT ENGINEER | JUNIOR ENGINEER | ORD/000101/2024-2025 | 2398/CMD | 02/08/2024 | 90 | MS S G ENTERPRISE | 53.43 | 0.00 | 0 | 0 |
7 | PURBA BARDHAMAN | Kalna - I | Central Mechanical | NIRALGACHHI PIPED WATER SUPPLY SCHEME , SM/14436 | New | Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Niralgachhi Water Supply Scheme [ Block- KALNA-1 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. | ASSISTANT ENGINEER | JUNIOR ENGINEER | ORD/000759/2023-2024 | 4061/CMD | 29/08/2023 | 30 | M/S, S.S. ENTERPRISE. | 27.79 | 0.00 | 0 | 0 |
Total | 1,220.86 | 6.63 | 0.54 |