Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 691.42 338.83 49  
1 PURBA BARDHAMAN Katwa - II Burdwan Division JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New JAGADANANDAPUR Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 400 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under KATWA -II Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE ORD/000711/2022-2023 777/BWD 24/02/2023 365 MANASH GHOSH 562.08 317.27 56.45 78
2 PURBA BARDHAMAN Katwa - II Burdwan Division JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New Material Requisition To Resource Division RTOR000062/2022-2023 1246/BWD 17/03/2023 Resource Division 17.02 0.00 0 0
3 PURBA BARDHAMAN Katwa - II Burdwan Division JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New Material Requisition To Resource Division RTOR000096/2022-2023 1638/BWD 06/04/2023 Resource Division 1.10 0.00 0 0
4 PURBA BARDHAMAN Katwa - II Burdwan Division JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New Material Requisition To Resource Division RTOR000786/2023-2024 327/BWD 24/01/2024 Resource Division 22.74 0.00 0 0
5 PURBA BARDHAMAN Katwa - II Central Mechanical JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New New service connection charges for Jagadanandapur W/S Scheme TW-1 BILL/00694/2023-2024 BP-2023-24-36 27/06/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.38 0.00 0 0
6 PURBA BARDHAMAN Katwa - II Central Mechanical JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New New service connection charges for Jagadanandapur PWSS TW-2 BILL/00797/2023-2024 BP-2023-24-85 26/07/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 5.95 0.00 0 0
7 PURBA BARDHAMAN Katwa - II Central Mechanical JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Mulgram & others water supply scheme under Katwa-II Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER Junior Engineer ORD/000070/2024-2025 2409/CMD 02/08/2024 90 DUTTA ENTERPRISE 50.18 0.00 0 0
8 PURBA BARDHAMAN Katwa - II Central Mechanical JAGADANANDAPUR PIPED WATER SUPPLY SCHEME , SM/14054 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Jagadanandapur Water Supply Scheme [ Block- KATWA-2 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. Driller In-Charge Junior Engineer ORD/000126/2023-2024 2659/CMD 16/06/2023 30 PADMA ENGINEERING CO. 28.97 21.56 74.42 60
Total 691.44 338.84 49