Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 730.89 40.98 5.61  
1 PURBA BARDHAMAN Ausgram - II Durgapur W/S Division AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Formal Work Order for Additional work for laying 200 mm dia HDPE pipe line and other necessary allied works Amarpur & Bhedia Piped W/S Scheme, Block- Aushgram-2, Dist- Purba Bardhaman under Durgapur W/S Division, PHE Dte. Assistant Engineer-II JUNIOR ENGINEER-1,JUNIOR ENGINEER-2 ORD/000141/2024-2025 1291/DWSD 06/09/2024 90 SAIKAT RAY 196.61 0.00 0 0
2 PURBA BARDHAMAN Ausgram - II Burdwan Division AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Sinking of Tube-wells, LDS, Rising Main, FHTC, Construction of 200 cum capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation, construction of switch rooms, boundary walls with gates, land development, internal drains and internal pathways for AMARPUR Piped Water Supply Scheme under Ausgram-II Block, District:- Purba-Bardhaman [NEW SCHEME] ORD/000820/2023-2024 4952/BWD 17/11/2023 365 SUJAY KUMAR RAY 344.32 35.55 10.32 50
3 PURBA BARDHAMAN Ausgram - II Burdwan Division AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Material Requisition To Resource Division RTOR000043/2023-2024 1962/BWD 25/04/2023 Resource Division 9.35 0.00 0 0
4 PURBA BARDHAMAN Ausgram - II Burdwan Division AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Material Requisition To Resource Division RTOR000208/2023-2024 2155/BWD 10/05/2023 Resource Division 20.19 0.00 0 0
5 PURBA BARDHAMAN Ausgram - II Burdwan Division AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Material Requisition To Resource Division RTOR000611/2023-2024 4932/BWD 10/11/2023 Resource Division 30.36 0.00 0 0
6 PURBA BARDHAMAN Ausgram - II Central Mechanical AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New NEW SERVICE CONNECTION FOR AMARPUR PWSS PH 1. BILL/02866/2023-2024 BP-2023-24-604 06/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.37 0.00 0 0
7 PURBA BARDHAMAN Ausgram - II Central Mechanical AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New NEW SERVICE CONNECTION FOR AMARPUR PWSS PH 2. BILL/02867/2023-2024 BP-2023-24-605 06/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 2.88 0.00 0 0
8 PURBA BARDHAMAN Ausgram - II Central Mechanical AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Chora, Kalaijhuti & others water supply scheme under Ausgram-2 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. Driller In-Charge JUNIOR ENGINEER ORD/000143/2024-2025 2405/CMD 02/08/2024 90 NABAUDYOG ELECTRICAL ENGINEERING CO-OPERATIVE SOCIETY LTD 95.26 0.00 0 0
9 PURBA BARDHAMAN Ausgram - II Central Mechanical AMARPUR PIPED WATER SUPPLY SCHEME , SM/13967 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Amarpur Water Supply Scheme [ Block- Ausgram-2 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. Driller In-Charge JUNIOR ENGINEER ORD/000913/2023-2024 4177/CMD 29/08/2023 30 AMUSAR IMPEX PVT. LTD. 28.55 5.43 19.02 96
Total 730.91 40.98 5.61