Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 715.52 168.26 23.52  
1 PURBA BARDHAMAN Khandaghosh Burdwan Division GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New GOPALBERA Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 300 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Khandaghosh Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer, Durgapur Sub Division, P.H.E. Dte Junior Engineer2, Durgapur Sub-Division, PHE Dte. ORD/000081/2023-2024 2079/BWD 04/05/2023 365 KHAN ENTERPRISE 588.35 156.88 26.66 50
2 PURBA BARDHAMAN Khandaghosh Burdwan Division GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New Material Requisition To Resource Division RTOR000105/2023-2024 1965/BWD 26/04/2023 Resource Division 9.42 0.00 0 0
3 PURBA BARDHAMAN Khandaghosh Burdwan Division GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New Material Requisition To Resource Division RTOR000192/2023-2024 2155/BWD 10/05/2023 Resource Division 11.22 0.00 0 0
4 PURBA BARDHAMAN Khandaghosh Burdwan Division GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New Material Requisition To Resource Division RTOR000715/2023-2024 5269/BWD 30/11/2023 Resource Division 21.07 0.00 0 0
5 PURBA BARDHAMAN Khandaghosh Central Mechanical GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New New service connection for Gopalbera PWSS TW -1. BILL/02415/2023-2024 BP-2023-24-513 08/02/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 4.42 0.00 0 0
6 PURBA BARDHAMAN Khandaghosh Central Mechanical GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New New service connection for Gopalbera PWSS TW -2. BILL/02416/2023-2024 BP-2023-24-514 08/02/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 6.28 0.00 0 0
7 PURBA BARDHAMAN Khandaghosh Central Mechanical GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at KHEJURHATI & others water supply scheme under Khandoghosh Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman ASSISTANT ENGINEER Junior Engineer ORD/000071/2024-2025 2391/CMD 02/08/2024 90 C.M. ENTERPRISE 45.81 0.00 0 0
8 PURBA BARDHAMAN Khandaghosh Central Mechanical GOPALBERA PIPED WATER SUPPLY SCHEME , SM/13905 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Gopalbera Water Supply Scheme [ Block- Khandoghosh ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER Junior Engineer ORD/000732/2023-2024 4042/CMD 29/08/2023 30 ASHIM UDYOG 28.95 11.38 39.31 0
Total 715.51 168.26 23.52