Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 1,831.19 199.22 10.88  
1 PURBA BARDHAMAN Khandaghosh Burdwan Division AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New Different works related (sinking of Tube-wells, LDSs, Rising Mains, FHTCs, Construction of different capacity RCC OHRs each with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drains and internal pathways at different TW site) to AMRA, BALABATI, UKHRID & RUPSA Piped Water Supply Scheme under KHANDAGHOSH Block, District:- Purba Bardhaman [NEW SCHEME] Assistant Engineer, Durgapur Sub Division, P.H.E. Dte Junior Engineer2, Durgapur Sub-Division, PHE Dte. ORD/000008/2023-2024 1726/BWD 13/04/2023 365 S.P. CONSTRUCTION 1,710.27 198.05 11.58 45
2 PURBA BARDHAMAN Khandaghosh Burdwan Division AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New Material Requisition To Resource Division RTOR000194/2023-2024 2155/BWD 10/05/2023 Resource Division 15.41 0.00 0 0
3 PURBA BARDHAMAN Khandaghosh Burdwan Division AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New Material Requisition To Resource Division RTOR000702/2023-2024 5049/BWD 23/11/2023 Resource Division 20.46 0.00 0 0
4 PURBA BARDHAMAN Khandaghosh Central Mechanical AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New New service connection charges for Amra PWSS TW-1 BILL/01474/2023-2024 BP-2023-24-172 29/09/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.84 0.00 0 0
5 PURBA BARDHAMAN Khandaghosh Central Mechanical AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New New service connection charges for Amra PWSS TW-2 BILL/01475/2023-2024 BP-2023-24-173 29/09/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 6.42 0.00 0 0
6 PURBA BARDHAMAN Khandaghosh Central Mechanical AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at KHEJURHATI & others water supply scheme under Khandoghosh Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman ASSISTANT ENGINEER Junior Engineer ORD/000071/2024-2025 2391/CMD 02/08/2024 90 C.M. ENTERPRISE 45.81 0.00 0 0
7 PURBA BARDHAMAN Khandaghosh Central Mechanical AMRA PIPED WATER SUPPLY SCHEME , SM/13454 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Amra Water Supply Scheme [ Block- Khandogosh ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000678/2023-2024 4010/CMD 29/08/2023 30 M/S. SWAPAN BANERJEE 28.98 1.17 4.04 0
Total 1,831.18 199.21 10.88