Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 485.06 | 85.29 | 17.58 | ||||||||||||||
1 | PURBA BARDHAMAN | Memari - II | Burdwan Division | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | BARA PALASHAN Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 250 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Memari-II Block, District:- Purba-Bardhaman [NEW SCHEME] | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | JUNIOR ENGINEER RWS BURDWAN SUB-DIVISION PHE DTE | ORD/000111/2023-2024 | 2300/BWD | 19/05/2023 | 365 | MLG CONSTRUCTION | 358.59 | 79.51 | 22.17 | 52 |
2 | PURBA BARDHAMAN | Memari - II | Burdwan Division | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Continuation work order for "Supply of one No. Diesel Driven Ambassador Car on hire basis for the office of the Assistant Engineer, Burdwan Sub-Division, PHE Dte. (Period from 01-06-2024 to 31-08-2024" | JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE | ORD/000228/2024-2025 | 918/BSD | 28/05/2024 | 92 | SK. ASFIA | 1.20 | 0.00 | 0 | 60 | |
3 | PURBA BARDHAMAN | Memari - II | Burdwan Division | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Material Requisition To Resource Division | RTOR000234/2023-2024 | 2197/BWD | 12/05/2023 | Resource Division | 23.40 | 0.00 | 0 | 0 | |||
4 | PURBA BARDHAMAN | Memari - II | Burdwan Division | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Material Requisition To Resource Division | RTOR000501/2023-2024 | 4025/BWD | 08/09/2023 | Resource Division | 6.08 | 0.00 | 0 | 0 | |||
5 | PURBA BARDHAMAN | Memari - II | Burdwan Division | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Material Requisition To Resource Division | RTOR000653/2023-2024 | 5099/BWD | 23/11/2023 | Resource Division | 20.46 | 0.00 | 0 | 0 | |||
6 | PURBA BARDHAMAN | Memari - II | Central Mechanical | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | New service connection at Barapalasan PWSS TW -2 | BILL/02331/2023-2024 | BP-2023-24-448 | 29/01/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 5.18 | 0.00 | 0 | 0 | |||
7 | PURBA BARDHAMAN | Memari - II | Central Mechanical | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | New service connection at Barapalasan PWSS TW -1. | BILL/02332/2023-2024 | BP-2023-24-447 | 29/01/2024 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) | 3.90 | 0.00 | 0 | 0 | |||
8 | PURBA BARDHAMAN | Memari - II | Central Mechanical | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Installation of two tank chlorination system, Yard lighting arrangement & allied works at NOAHATI & others water supply scheme under Memari-II Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. | ASSISTANT ENGINEER | Junior Engineer | ORD/000102/2024-2025 | 2395/CMD | 02/08/2024 | 90 | S.G. TECHNICAL SERVICES | 36.99 | 0.00 | 0 | 0 |
9 | PURBA BARDHAMAN | Memari - II | Central Mechanical | BARAPALASHAN PIPED WATER SUPPLY SCHEME , SM/13423 | New | Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Barapalashan Water Supply Scheme [ Block- Memari-2 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. | ASSISTANT ENGINEER | Junior Engineer | ORD/000711/2023-2024 | 4022/CMD | 29/08/2023 | 30 | MITRA ENTERPRISE | 29.26 | 5.78 | 19.75 | 0 |
Total | 485.05 | 85.28 | 17.58 |