Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 677.93 210.8 31.09  
1 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New Restoration of hard shouldering and flank damaged during laying of PHE pipeline at Samanti village road from 0.00 Kmp to 3.00 Kmp within Samanti PWSS. BILL/00138/2024-2025 226/JJM 14/05/2024 EXECUTIVE ENGINEER-I, BURDWAN DIVISION, P.W.D. 5.08 0.00 0 0
2 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New Supply & delivery of different dia. MJ Coller for FHTC as well as smooth running of different W/S. Schemes under Burdwan Division, P.H.E. Dte. [i.e. (1) Magra PWSS, Memari-I Block, (2) Kuchut PWSS, Memari - II Block, (3) Khundkuri PWSS, Khandaghosh Block & (4) Samanti PWSS, Burdwan - II Block)] ORD/000653/2023-2024 4076/BWD 13/09/2023 20 SSPR VALVE MANUFACTURING PVT LTD. 20.63 0.00 0 100
3 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New SAMANTI Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 250 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under BARDHAMAN-II Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. Junior Engineer, Burdwan Sadar Sub-Division ORD/000802/2022-2023 1536/BWD 29/03/2023 365 G.B. CONSTRUCTION & CO. 504.69 199.37 39.5 36
4 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New Material Requisition To Resource Division RTOR000015/2023-2024 1962/BWD 25/04/2023 Resource Division 10.45 0.00 0 0
5 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New Material Requisition To Resource Division RTOR000170/2023-2024 2155/BWD 10/05/2023 Resource Division 23.19 0.00 0 0
6 PURBA BARDHAMAN Burdwan - II Burdwan Division Samanti Piped Water Supply Scheme , SM/13319 New Material Requisition To Resource Division RTOR000732/2023-2024 5237/BWD 30/11/2023 Resource Division 21.07 0.00 0 0
7 PURBA BARDHAMAN Burdwan - II Central Mechanical Samanti Piped Water Supply Scheme , SM/13319 New New service connection charges for Samanti PWSS TW-1 BILL/00886/2023-2024 BP-2023-24-112 10/08/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 4.10 0.00 0 0
8 PURBA BARDHAMAN Burdwan - II Central Mechanical Samanti Piped Water Supply Scheme , SM/13319 New New service connection for Samanti W/S scheme TW No-2 BILL/02273/2023-2024 BP-2023-24-411 19/01/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 6.60 0.00 0 0
9 PURBA BARDHAMAN Burdwan - II Central Mechanical Samanti Piped Water Supply Scheme , SM/13319 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at KUSHA & others water supply scheme under Bardhaman-II Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman ASSISTANT ENGINEER Junior Engineer ORD/000065/2024-2025 2389/CMD 02/08/2024 90 DILIP MAHATO 53.14 0.00 0 0
10 PURBA BARDHAMAN Burdwan - II Central Mechanical Samanti Piped Water Supply Scheme , SM/13319 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Samanti Water Supply Scheme [ Block- Burdwan-2 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER Junior Engineer ORD/000194/2023-2024 2979/CMD 18/07/2023 30 MS DAS ELECTRIC CO 28.98 11.43 39.44 95
Total 677.93 210.80 31.1