Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
19 905.05 761.53 84.14  
1 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation New service connection quotation from WBSEDCL of Augmentation of Baidyapur Z-II (T.W.-3) under Burdwan Division, PHE Dte. BILL/00098/2023-2024 194/JJM 31/05/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 4.56 0.00 0 0
2 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Augmentation of Baidyapur (Zone-I & II) Piped Water Supply Scheme with LDS, FHTC, Rising main, Construction of 200 cum capacity OHR with 20.0 mtr. Staging height inclusive of soil investigation including repairing of OHR, boundary walls & switch rooms under Kalna-II Block, District:- Purba-Burdwan. Assistant Engineer JUNIOR ENGINEER R.W.S. BURDWAN SUB-DIVISION PHE DTE ORD/000116/2022-2023 2859/BWD 22/06/2022 365 SUPRITI ENTERPRISE 734.07 712.21 97.02 60
3 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Sinking of 250 X 150mm dia Tube Well 150 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) for Aug. of BAIDYAPUR (Z-I) PWSS, Block - Kalna - II and NANDAI PWSS, Block - Kalna - I Piped Water Supply Scheme, Dist - Purba Bardhaman under Burdwan Division, PHE Dte. [For 02 Nos. Tube well]. ORD/000151/2023-2024 2424/BWD 30/05/2023 45 KOUSIK MALLICK 19.84 9.14 46.07 100
4 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply of various D.I. Mechanical joints & specials for Aug. of SATGACHI & Aug. of BAIDYAPUR Piped W/S. Scheme within Kalna Sub-Division under Burdwan Division, PHE. Dte. [Part-B]. AE(HQs) ORD/000304/2024-2025 2827/BWD 19/07/2024 20 KEJRIWAL CASTINGS LIMITED 4.82 0.00 0 0
5 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply of various D.I. Mechanical joints & specials for Aug. of SATGACHI & Aug. of BAIDYAPUR Piped W/S. Scheme within Kalna Sub-Division under Burdwan Division, PHE. Dte. [Part-C]. AE(HQs) ORD/000308/2024-2025 2831/BWD 19/07/2024 20 JINDAL SAW LTD. 4.63 0.00 0 0
6 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply of various D.I. Mechanical joints & specials for Aug. of SATGACHI & Aug. of BAIDYAPUR Piped W/S. Scheme within Kalna Sub-Division under Burdwan Division, PHE. Dte. [Part-A]. AE(HQs) ORD/000315/2024-2025 2839/BWD 19/07/2024 20 ELECTROSTEEL CASTING LIMITED 4.95 0.00 0 0
7 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Construction of switch rooms & Rising main at different TW site for Baidyapur (Zone-I) Piped Water Supply Scheme under Kalna - II Block, District:- Purba-Bardhaman under Burdwan Division, PHE. Dte. Assistant Engineer JUNIOR ENGINEER RWS KALNA2 ORD/000529/2023-2024 3626/BWD 21/08/2023 60 M/S UNIQUE 9.11 3.34 36.66 65
8 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Sinking of 250 X 150mm dia Tube Well 150 mtr. Depth by D.R. Rig method using UPVC pipe (CM) and UPVC Medium Well Screen (RMS) for 2nd TW Site of Aug. of BAIDYAPUR (Z-II) & its adjoining mouzas Piped Water Supply Scheme, Block ? Kalna ? II, Dist - Purba Bardhaman under Burdwan Division, PHE Dte._2ND CALL. Assistant Engineer ORD/000567/2022-2023 5274/BWD 30/11/2022 30 SUSUNIA GP CO. OPERATIVE LABOUR CONTRACT AND CONSTRUCTION SOCIETY LTD. 7.33 6.97 95.09 0
9 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Preparation of DPR for augmentation of Baidyapur W/S Scheme (Zone-I & II) within Kalna Sub-Division under Burdwan Division, PHE Dte. (Sl No-A) Assistant Engineer ORD/000568/2021-2022 203/KSD 23/02/2022 21 INDRANIL DUTTA & ASSOCIATES 4.19 4.17 99.52 1
10 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Additional pipe laying of HDPE pipeline & providing FHTC work at Sanpukur, Mirhat village under BAIDYAPUR Water Supply Scheme within Kalna Sub-Division under Burdwan Division, PHE Dte. Assistant Engineer JUNIOR ENGINEER RWS KALNA2 ORD/000871/2023-2024 5308/BWD 01/12/2023 30 GENUINE ENGINEERING CO-OP. SOCIETY LTD. 35.01 13.02 37.19 1
11 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Work Order for "Restoration in pipe connection of Augmentation scheme of Baidyapur Zone-II Piped Water Supply Scheme under Kalna Sub-Division under Burdwan Division, PHE Dte." (SL-3) Assistant Engineer JUNIOR ENGINEER RWS KALNA2 ORD/001133/2023-2024 2062/KSD 23/02/2024 20 YOUNG ENGINEERS CO.-OPERATIVE SOCIETY LTD. 1.37 0.00 0 0
12 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Work Order for "Renovation of Pump House for Augmentation 1 of Baidyapur (Zone-II) Piped Water Supply Scheme within Kalna Sub-Division under Burdwan Division, PHE Dte." Assistant Engineer JUNIOR ENGINEER RWS KALNA2 ORD/001241/2023-2024 1953/KSD 05/02/2024 25 ER CONSTRUCTION & GENERAL ORDER SUPPLIER 0.59 0.11 18.64 100
13 PURBA BARDHAMAN Burdwan Division AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Material Requisition To Resource Division RTOR000001/2022-2023 3272/BWD 29/07/2022 Resource Division 31.47 0.00 0 0
14 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Quotation for new service connection at Baidyapur Zone-2 PWSS PH-3 BILL/00390/2024-2025 BP-2024-25-200 18/07/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 4.14 0.00 0 0
15 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Augmentation of BAIDYAPUR PWSS under CMD, PHE Dte., Dist.- Purba-Bardhaman ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000912/2022-2023 1036/CMD 02/03/2023 30 BEHERA ENTERPRISE 11.46 11.13 97.12 80
16 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.- 5 & 6 at Augumentation of BAIDYAPUR Water Supply Scheme [BLOCK- KALNA-2] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/001618/2023-2024 1542/CMD 05/03/2024 60 PROGRESSIVE ENGINEERS CO-OPERATIVE SOCIETY LIMITED 24.62 0.00 0 0
17 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply and delivery of different Electro-mechanical items for Baidyapur zone-1 Water Supply Scheme PH 1 replacement T.W (part-1) under CMD, PHE Dte., Dist.- Purba-Bardhaman ASSISTANT ENGINEER JUNIOR ENGINEER ORD/001670/2023-2024 64/CMSD 11/01/2024 12 SUBRATA BHADRA 0.96 0.47 48.96 100
18 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation House wiring, double earthing and allied works for Baidyapur zone-1 Water Supply Scheme PH 1 replacement T.W (part-2) under CMD, PHE Dte., Dist.- Purba-Bardhaman ASSISTANT ENGINEER JUNIOR ENGINEER ORD/001674/2023-2024 80/CMSD 15/01/2024 12 SUBRATA BHADRA 0.97 0.49 50.52 100
19 PURBA BARDHAMAN Central Mechanical AGUMENTATION OF GROUND WATER BASED BAIDYAPUR PWSS TO ACCOMMODATE FHTC IN KALNA-II BLOCK UNDER KALNA SUB DIVISION OF BURDWAN DIVISION IN PURBA BARDHAMAN DISTRICT (ZONE-I & ZONE-II) , SM/10032 Augmentation Supply & Installation of Chlorination System for Tube well No.-1 at Baidyapur (zone-1) Water Supply Scheme under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/001863/2023-2024 461/CMSD 21/03/2024 12 SUDIKSHA CONSTRUCTION 0.96 0.48 50 100
Total 905.05 761.52 84.14