Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 3,245.92 185.84 5.73  
1 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Route Survey & Preparation of DPR for Sankari W/S Scheme under Khandaghosh Block under Burdwan Sub-Division under Burdwan Division PHE Dte. Sl No.10. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000498/2021-2022 185/BSD 31/01/2022 30 RADIANT 2.52 2.52 100 1
2 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Augmentation of SANKARI Piped Water Supply Scheme with LDS, Rising Main, Constn. of 250 cum capacity OHR with 20.0 Mtr. staging height inclusive of soil test & FHTC under Khandaghosh Block, District - Purba Bardhaman. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000527/2021-2022 1119/BWD 28/02/2022 360 UNIQUE AGENCY 208.48 183.32 87.93 100
3 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Supply and delivery of different dia. CIDF sluice valve for Augmentation of SANKARI Piped Water Supply Scheme under Burdwan Division, P.H.E. Dte._SL No. 06 Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000617/2021-2022 140/AE/HQ 16/03/2022 10 MAKALI ENGINEERING CORPORATION 4.52 0.00 0 0
4 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Material Requisition To Resource Division RTOR000054/2021-2022 529/BWD 27/01/2022 Resource Division 6.82 0.00 0 0
5 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Material Requisition To Resource Division RTOR000093/2021-2022 903/BWD 15/02/2022 Resource Division 18.21 0.00 0 0
6 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Material Requisition To Resource Division RTOR000204/2021-2022 1527/BWD 15/03/2022 Resource Division 0.37 0.00 0 0
7 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based SANKARI PWSS to accommodate FHTC in KHANDOGHOSH block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09405 Augmentation Supply of materials for different water supply scheme under Burdwan Division, PHE Dte. VCH/001578/2021-2022 1207/DW 10/03/2022 EXECUTIVE ENGINEER, RESOURCES DIVISION, P.H.E. DTE. 3,005.00 0.00 0 0
Total 3,245.92 185.83 5.73