Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
6 | 45.45 | 11.22 | 24.69 | ||||||||||||||
1 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Providing 22 Nos.FHTC at IDILPUR & FAKIRPUR village for declearation of SWAJALGRAM under FAKIRPUR Piped Water Supply Scheme, Block- Burdwan-I within Burdwan Sub Division under Burdwan Division PHE Dte. | JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE | ORD/000166/2024-2025 | 1035/BSD | 10/06/2024 | 30 | IMPULSE INTERNATIONAL | 0.75 | 0.00 | 0 | 0 | ||
2 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Providing 50 Nos. FHTC at Bongapur Casimama village for deceleration of SWAJALGRAM under FAKIRPUR Piped Water Supply Scheme , Block- Burdwan-I within Burdwan Sub Division under Burdwan Division PHE | JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE | ORD/000297/2024-2025 | 1279/BSD | 12/07/2024 | 45 | S.M. ENTERPRISE | 2.32 | 0.00 | 0 | 0 | ||
3 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Providing Balance Functional Household Tap Connection (FHTC)for Swajal Gram from existing distribution system within the command area of Idilpur & Fakirpur village under Fakirpur Piped W/S.Scheme under Burdwan-I Block of Burdwan Sub-Division under Burdwan Division, PHE Dte. Gr. I | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | ORD/000346/2022-2023 | 1380/BSD | 05/08/2022 | 5 | BAMDEB CONSTRUCTION & CO | 0.96 | 0.96 | 100 | 100 | ||
4 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Construction of boundary wall at Head works site of Fakirpur water supply scheme under Bardhaman-I Block under Burdwan Division, PHE Dte.[Length-50.20 Mtr][Part-B][South & West Side][Gr.-C] | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | ORD/000558/2021-2022 | 1026/BSD | 05/08/2021 | 45 | AYSAN KHAN | 3.77 | 0.00 | 0 | 1 | ||
5 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Providing Functional Household Tap Connection (FHTC) from existing distribution system within the command area of FAKIRPUR Piped Water Supply Scheme at Fakirpur & Bongpur village (Mouza), Burdwan - I Block under Burdwan Division, PHE Dte._2ND CALL. | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | ORD/000641/2020-2021 | 355/BWD | 15/01/2021 | 45 | AYSAN KHAN | 36.69 | 10.26 | 27.96 | 1 | ||
6 | PURBA BARDHAMAN | Burdwan Division | Providing Functional Household Tap Connection (FHTC) by retrofitting within the command area of Fakirpur Piped Water Supply Scheme at Burdwan-I Block , SM/07797 | Retrofitting | Providing Balance Functional Household Tap Connection(FHTC)for Swajal Gram from existing distribution system within the command area of Idilpur & Fakirpur Village under of FAKIRPUR W.S.Scheme of Burdwan-I Block of Burdwan Sub-Division under Burdwan Division, PHE Dte. | Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. | JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE | ORD/000847/2022-2023 | 1380-A/BSD | 05/08/2022 | 5 | BAMDEB CONSTRUCTION & CO | 0.96 | 0.00 | 0 | 0 | |
Total | 45.45 | 11.22 | 24.68 |