Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 3,718.81 236.37 6.36  
1 PURBA BARDHAMAN Galsi - I Durgapur W/S Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Formal Work Order for the work of Sinking of 3 nos 300 x 200mm dia Tube Well-150 mtr and 10 Nos 200 x 200 mm dia River Bank Tube Well- 51 mtr with Construction of Pump House Cum Switch Room Chlorine Room under SHILLA PWSS (JJM) Block- Galsi-I, Distric- Purba Bardhaman under Durgapur W/S Division, PHE Dte Assistant Engineer-II JUNIOR ENGINEER-1 ORD/000060/2024-2025 885/DWSD 26/06/2024 120 M/S S. CHOUDHURY 120.44 0.00 0 0
2 PURBA BARDHAMAN Galsi - I Durgapur W/S Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Acceptance cum Formal Work Order for Design Engineering Services of Survey, General arrangement drawing, Pile foundation design and drawings, Pipe Pedestal and BOM, Structural design design and drawing, Fabrication drawings for 26 Numbers different dia meter pipe crossing Pipe Bridge at "PURANGAN (Zone-I, II, III), 11 Nos. Mouzas under PURSHA and UCHCHGRAM, SHILLA (Zone-I, II, III, IV), TAHER PUR (Zone-I, II, III) and KHANO (Zone-I and II) sites under Durgapur W/S Division,PHE Dte. Assistant Engineer-II JUNIOR ENGINEER-2 ORD/000105/2024-2025 1058/DWSD 25/07/2024 90 ASTER CONSULTANCY 47.43 0.00 0 0
3 PURBA BARDHAMAN Galsi - I Durgapur W/S Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Acceptance cum Formal Work Order for the work of Hiring of LUXURY Diesel Ambassador Car (Inspection Vehicle) for using of the Junior Engineers for the office of the Executive Engineer, Durgapur Water Supply Division, Public Health Engineering Dte at Fagupur, Nababhat, Purba Bardhaman for the period of 01.08.2024 to 31.01.2025 (6 Months) Assistant Engineer-I JUNIOR ENGINEER-2 ORD/000121/2024-2025 1108/DWSD 01/08/2024 180 SIDDHARTH ENTERPRISE 0.82 0.80 97.56 0
4 PURBA BARDHAMAN Galsi - I Burdwan Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Sub Surface Based Piped Water Supply Scheme with LDS, FHTC, Construction of different capacity RCC OHRs with 20.0 mtr. with Staging height including soil investigation, Construction of CWR, Chlorine Room, Guard Room, Sub Station Building, High Lift Pump House Boundary walls with gates, land development, drain and internal pathway of SHILLA Piped Water Supply Scheme under Galsi-I Block, District:- Purba-Bardhaman [NEW SCHEME] ORD/000455/2023-2024 3437/BWD 08/08/2023 365 M/S S. CHOUDHURY 2,687.54 235.57 8.77 45
5 PURBA BARDHAMAN Galsi - I Burdwan Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Hydro-geological study of Sub Surface Water Flow/Storage Characteristics for Creation of Sustainable Source and Estimation of Sustainable Yield (5 Nos of Schemes) in Purba Bardhaman District, West Bengal towards implementation of water supply project. ORD/000872/2023-2024 5324/BWD 01/12/2023 120 THE REGISTRAR JADAVPUR UNIVERSITY 113.34 0.00 0 20
6 PURBA BARDHAMAN Galsi - I Burdwan Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Material Requisition To Resource Division RTOR000309/2023-2024 2197/BWD 12/05/2023 Resource Division 11.39 0.00 0 0
7 PURBA BARDHAMAN Galsi - I Burdwan Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Material Requisition To Resource Division RTOR000440/2023-2024 3847/BWD 01/09/2023 Resource Division 460.56 0.00 0 0
8 PURBA BARDHAMAN Galsi - I Burdwan Division SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Material Requisition To Resource Division RTOR000774/2023-2024 207/BWD 10/01/2024 Resource Division 57.55 0.00 0 0
9 PURBA BARDHAMAN Galsi - I Central Mechanical SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Quotation for new service connection Shilla PWSS TW No. 3. BILL/00781/2024-2025 null 10/09/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 8.32 0.00 0 0
10 PURBA BARDHAMAN Galsi - I Central Mechanical SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Quotation for new service connection at Shilla PWSS (Naba Khanda) Zone-I. BILL/00783/2024-2025 null 10/09/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 7.26 0.00 0 0
11 PURBA BARDHAMAN Galsi - I Central Mechanical SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Providing Electro-mechanical accessories and others for Shilla & Adjoining moujas water supply scheme [ Block Galsi- I ] under Central Mechanical Division PHE Dte. ORD/001436/2023-2024 1342/CMD 08/02/2024 360 WEST BENGAL ENGINEERING CO. 164.44 0.00 0 0
12 PURBA BARDHAMAN Galsi - I Central Drilling SHILLA PIPED WATER SUPPLY SCHEME , SM/18344 New Construction of Tube Well (300 MM x 200 MM x Depth 500 Mtr) for Shilla W/S Scheme(T/W -I) Zone-IV, Block- Galsi-I, Purba Bardhaman District by Central Drilling Division, P.H. Engineering Dte. Driller In Charge Junior Engineer ORD/000216/2023-2024 2236/CDD 11/03/2024 60 SATYAJIT GHOSH 39.72 0.00 0 0
Total 3,718.82 236.37 6.36