Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 1,779.85 49.51 2.78  
1 BIRBHUM Rampurhat - I Birbhum Division Ayas Piped Water Supply Scheme. , SM/18669 New Sinking of 250 X 150 mm Dia (through) and 25 m deep tubewell , 5.90 m X 4.10 m Pump room/ Chlorine room with sanitary arrangements, 4.10 m X 3.50 m Pump house without sanitary arrangements, 8.00 m X 8.00 m Pump room/ Chlorine room with sanitary arrangements, 350 CuM, 300 CuM, 150 CuM capacity O.H.R. for Zone-I, II and III respectively, 300 CuM CWR, Boundary wall, Soil Investigation, Land development, Rising main, Laying distribution, road restoration for Zone-I, II and III and Providing functional household tap connection related to water supply scheme at AYAS & its adjoining mouzas water supply scheme within RAMPURHAT-I Block including supply of all labour & materials under BIRBHUM Division, PHE Dte". AE JE1,JE3 ORD/000088/2024-2025 1949/BHM 04/07/2024 365 PRADIP KUMAR DEB, 103/4 NAINAN PARA LANE , KOLKATA-700036 1,332.94 0.00 0 0
2 BIRBHUM Rampurhat - I Birbhum Division Ayas Piped Water Supply Scheme. , SM/18669 New Material Requisition To Resource Division RTOR000014/2024-2025 2389/BHM 27/08/2024 Resource Division 42.26 0.00 0 0
3 BIRBHUM Rampurhat - I Birbhum Division Ayas Piped Water Supply Scheme. , SM/18669 New Material Requisition To Resource Division RTOR000093/2023-2024 1495/BHM 25/04/2023 Resource Division 249.36 0.00 0 0
4 BIRBHUM Rampurhat - I Bolpur Mechanical Ayas Piped Water Supply Scheme. , SM/18669 New Supply & Installation of Low lift Pumping Mchinery and other allied work for AYAS & Adjoining moujas water supply scheme under within Rampurhat - I Block Bolpur Mechanical Division PHE Dte. Assistant Engineer-III Junior Engineer ORD/000869/2023-2024 3389/BOL.MD 16/10/2023 90 S.K.ELECTRICALS 59.94 14.32 23.89 50
5 BIRBHUM Rampurhat - I Bolpur Mechanical Ayas Piped Water Supply Scheme. , SM/18669 New Supply and Installation of High lift Pumping Machinery and other allied work for AYAS and Adjoining moujas water supply scheme under within Rampurhat - I Block Bolpur Mechanical Division PHE Dte Assistant Engineer-III Junior Engineer ORD/000872/2023-2024 3372/Bol.MD 12/10/2023 90 SINHA ELECTRICALS 95.35 35.19 36.91 30
Total 1,779.86 49.50 2.78