Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 625.03 16.64 2.66  
1 BIRBHUM Rampurhat - II Birbhum Division Dhalla Piped Water Supply Scheme , SM/15256 New Construction of 5.90 m X 4.10 m Pump room/ Chlorine room with sanitary arrangements, 250 CuM OHR , Boundary wall, Soil Investigation, Land development, Rising main, Laying distribution, road restoration and Providing functional household tap connection related to water supply scheme at DHALLA & its adjoining mouzas water supply scheme within RAMPURHAT-II Block including supply of all labour & materials under BIRBHUM Division, PHE Dte. AE JE2 ORD/000113/2024-2025 2180/BHM 06/08/2024 365 RADIANT 497.94 0.00 0 0
2 BIRBHUM Rampurhat - II Birbhum Division Dhalla Piped Water Supply Scheme , SM/15256 New Continuation Work Order for Preparation & Submission of DPR for (DHALLA) Water Supply Scheme (Part-A) under Rampurhat-II Development Block. AE JE3 ORD/000787/2022-2023 294/RSD 07/09/2022 45 ECO CARE 2.76 2.59 93.84 100
3 BIRBHUM Rampurhat - II Birbhum Division Dhalla Piped Water Supply Scheme , SM/15256 New Continuation Work Order for Preparation & Submission of DPR for (DHALLA) Water Supply Scheme (Part-B) under Rampurhat-II Development Block. AE JE3 ORD/000798/2022-2023 383/RSD 27/09/2022 45 ECO CARE 3.27 2.86 87.46 100
4 BIRBHUM Rampurhat - II Birbhum Division Dhalla Piped Water Supply Scheme , SM/15256 New Material Requisition To Resource Division RTOR000025/2023-2024 1521/BHM 26/04/2023 Resource Division 55.13 0.00 0 0
5 BIRBHUM Rampurhat - II Birbhum Division Dhalla Piped Water Supply Scheme , SM/15256 New Material Requisition To Resource Division RTOR000041/2024-2025 2484/BHM 03/09/2024 Resource Division 13.92 0.00 0 0
6 BIRBHUM Rampurhat - II Bolpur Mechanical Dhalla Piped Water Supply Scheme , SM/15256 New Providing Electro-mechanical accessories and others for Dhalla PWSS at Rampurhat - II Block under Bolpur Mechanical Division PHE Dte. Assistant Engineer-III Junior Engineer ORD/000472/2023-2024 2225/Bol.MD 12/09/2023 60 QUAZI NOZRUL ISLAM 44.40 11.19 25.2 30
7 BIRBHUM Rampurhat - II Bolpur Mechanical Dhalla Piped Water Supply Scheme , SM/15256 New Supply and Installation of Submersible pumping machineries and other electromechanical equipments at Dhalla PWSS under Illambazar Block in the Dist of Birbhum under Bolpur Mechanical Division,P.H.E.Dte. Assistant Engineer Junior Engineer ORD/001235/2023-2024 520/BOL.MD 14/03/2024 60 AMITAVA CHAKRABORTY 7.61 0.00 0 0
Total 625.04 16.65 2.66