Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 609.06 2.42 0.4  
1 BIRBHUM Mayureswar - II Birbhum Division DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Different works related to Water Supply Scheme at DUNA & its adjoining mouzas Water Supply Scheme within MAYURESWAR-II Block including supply of all labour & materials under BIRBHUM Division, PHE Dte. AE JE3 ORD/000057/2023-2024 1249/BHM 17/04/2023 270 CREATIVE CONSTRUCTION 473.21 0.00 0 0
2 BIRBHUM Mayureswar - II Birbhum Division DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Continuation Work Order for Preparation & Submission of DPR for (DUNA) Water Supply Scheme (Part-A) under Mayureswar-II Development Block. AE JE3 ORD/000838/2022-2023 296/RSD 07/09/2022 45 ENVIROTECH SOLUTIONS 3.22 2.34 72.67 100
3 BIRBHUM Mayureswar - II Birbhum Division DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Continuation Work Order for Preparation & Submission of DPR for (DUNA) Water Supply Scheme (Part-B) under Mayureswar-II Development Block. AE JE3 ORD/000839/2022-2023 423/RSD 03/11/2022 45 ENVIROTECH SOLUTIONS 2.86 0.08 2.8 100
4 BIRBHUM Mayureswar - II Birbhum Division DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Material Requisition To Resource Division RTOR000051/2023-2024 1518/BHM 26/04/2023 Resource Division 36.07 0.00 0 0
5 BIRBHUM Mayureswar - II Birbhum Division DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Material Requisition To Resource Division RTOR000210/2023-2024 208/BHM 22/01/2024 Resource Division 1.54 0.00 0 0
6 BIRBHUM Mayureswar - II Bolpur Mechanical DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Supply, Delivewry and storage of vacuum operated gaseous Chlorination system for Duna PWSS, Block : Mayureswar-II under Bolpur Mechanical Division.PHE.DTE. Assistant Engineer-III Junior Engineer ORD/000515/2024-2025 3761/Bol.MD 12/09/2024 30 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 28.84 0.00 0 0
7 BIRBHUM Mayureswar - II Bolpur Mechanical DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Providing Electro-mechanical accessories and others for Duna PWSS at Mayureswar - II Block under Bolpur Mechanical Division PHE Dte. Assistant Engineer-III Junior Engineer ORD/000842/2023-2024 3281/BOL.MD 29/09/2023 60 DEY ENTERPRISE 55.70 0.00 0 60
8 BIRBHUM Mayureswar - II Bolpur Mechanical DUNA PIPED WATER SUPPLY SCHEME OF MAYURESWAR-II BLOCK UNDER BIRBHUM DISTRICT , SM/14675 New Supply and Installation of Submersible pumping machineries and other electromechanical equipments at Duna PWSS under Mayureswar - II Block in the Dist of Birbhum under Bolpur Mechanical Division,P.H.E.Dte. Assistant Engineer-III Junior Engineer ORD/001236/2023-2024 521/BOL.MD 14/03/2024 60 PRADIP KUMAR DHABAL 7.62 0.00 0 0
Total 609.06 2.42 0.4