Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 2,328.87 18.56 0.8  
1 BIRBHUM Dubrajpur Birbhum Division Paduma Piped Water Supply Scheme. , SM/14544 New Different works related to water supply scheme at PARULIA, KHANPUR & PADUMA and its adjoining mouzas water supply scheme within DUBRAJPUR Block including supply of all labour & materials under BIRBHUM Division, PHE Dte. AE JE3 ORD/000076/2023-2024 1425/BHM 25/04/2023 270 BIPIN KUMAR SINGH 2,248.63 0.00 0 20
2 BIRBHUM Dubrajpur Bolpur Mechanical Paduma Piped Water Supply Scheme. , SM/14544 New Providing Electro-mechanical accessories and others for Paduma PWSS at Dubrajpur Block under Bolpur Mechanical Division PHE Dte. Assistant Engineer-III Junior Engineer ORD/000397/2023-2024 2075/BOL.MD. 21/08/2023 90 S.P. CONSTRUCTION 80.24 18.56 23.13 40
Total 2,328.87 18.56 0.8