Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 1,055.42 | 30.07 | 2.85 | ||||||||||||||
1 | BIRBHUM | Sainthia | Birbhum Division | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | Different works related to water supply scheme at DERPUR, KURUMSAHA & MATIARA and its adjoining mouzas water supply scheme within SAINTHIA Block including supply of all labour & materials under Birbhum Division, PHE Dte. | AE | JE | ORD/000056/2023-2024 | 1245/BHM | 17/04/2023 | 270 | BRAHMA CONSTRUCTION COMPANY | 978.83 | 0.00 | 0 | 65 |
2 | BIRBHUM | Sainthia | Birbhum Division | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | Material Requisition To Resource Division | RTOR000051/2022-2023 | 1366/BHM | 24/04/2023 | Resource Division | 19.69 | 0.00 | 0 | 0 | |||
3 | BIRBHUM | Sainthia | Bolpur Mechanical | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | WBSEDCL QUOTATION FOR KURUMSAHA P.H.NO.I | BILL/00707/2023-2024 | BP-2023-2024-63 | 02/08/2023 | WBSEDCL | 3.85 | 0.00 | 0 | 0 | |||
4 | BIRBHUM | Sainthia | Bolpur Mechanical | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | wbsedcl quotation for kurumsaha p.h.no.ii ws scheme | BILL/00716/2023-2024 | BP-23-24-70 | 09/08/2023 | WBSEDCL | 3.91 | 0.00 | 0 | 0 | |||
5 | BIRBHUM | Sainthia | Bolpur Mechanical | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | Providing Electro-mechanical accessories and others for Kurumsaha & Adjoining moujas water supply scheme at Sainthia Block under Bolpur Mechanical Division PHE Dte. | Driller in Charge | Junior Engineer | ORD/000418/2023-2024 | 2090/Bol.MD | 22/08/2023 | 60 | MITRA ENTERPRISE | 28.04 | 11.99 | 42.76 | 80 |
6 | BIRBHUM | Sainthia | Central Drilling | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | PROVIDING DRLLING CREW AND OTHER ALLIED WORKS FOR CONSTRUCTION OF TUBE WELL (250MM X 150MM X 150 MTRS DEPTH) BY UTILISING DEPARTMENTAL MACHINERIES FOR Kurumsaha W/S SCHEME (TW-II), SAINTHIA BLOCK, UNDER BIRBHUM DISTRICT, CDD, PHE DTE. | Driller In Charge | Junior Engineer | ORD/000405/2022-2023 | 1428/CDD | 29/11/2022 | 30 | C.M. ENTERPRISE | 10.49 | 9.15 | 87.23 | 0 |
7 | BIRBHUM | Sainthia | Central Drilling | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | PROVIDING TUBE WELL MATERIALS, CONFORMING TO IS: 12818:2010 WITH OTHER WORKS AT SITE FOR CONSTRUCTION OF TUBE WELL IN KURUMSAHA PWSS (TW-I), SAINTHIA BLOCK, BIRBHUM DISTRICT UNDER CDD, PHE DTE. | ORD/000415/2022-2023 | 382/CMSD-I | 05/08/2022 | 15 | C.M. ENTERPRISE | 4.18 | 3.79 | 90.67 | 0 | ||
8 | BIRBHUM | Sainthia | Central Drilling | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | SUPPLY & DELIVERY OF CONSUMBLES WITH OTHER WORKS AT SITE FOR CONSTTRUCTION OF TUBE WELL IN KURUMSAHA PWSS (TW-I), BLOCK-SAINTHIA, BIRBHUM DISTRICT UNDER CDD, PHE DTE. | ORD/000416/2022-2023 | 390/CMSD-I | 05/08/2022 | 15 | C.M. ENTERPRISE | 2.66 | 2.64 | 99.25 | 0 | ||
9 | BIRBHUM | Sainthia | Central Drilling | Kurumsaha Piped Water Supply Scheme. , SM/13628 | New | PROVIDING DRILLING CREWS FOR CONSTRUCTION OF TUBE WELL BY DEPARTMENTAL RIG MACHINE IN KURUMSAHA PWSS (TW-I), BLOCK-SAINTHIA, BIRBHUM DISTRICT UNDER CDD, PHE DTE. | ORD/000417/2022-2023 | 398/CMSD-I | 05/08/2022 | 15 | C.M. ENTERPRISE | 3.77 | 2.50 | 66.31 | 0 | ||
Total | 1,055.41 | 30.07 | 2.85 |