Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 1,267.34 76.13 6.01  
1 MURSHIDABAD Central Drilling Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) ORD/000215/2023-2024 2235/CDD 11/03/2024 150 JHARGRAM SPV PRIVATE LIMITED 720.23 0.00 0 10
2 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Construction of Service Road for approach and Pump House at Augmentation of Bansgara Zone-I PWSS of Raninagar-II Block under Jal Jeevan Mission of Murshidabad District under Berhampore Division-I, PHE Dte. Assistant Engineer ORD/000045/2024-2025 1068/BD-I 03/07/2024 60 MAHATO ENTERPRISE 9.00 0.00 0 0
3 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation BANSGARA ZONE-I PWSS to accommodate construction of Boundary Wall under Jal Jivan Mission of RANINAGAR-II Block, Murshidabad District under Berhampore Division-I, PHE.Dte. Assistant Engineer ORD/000084/2024-2025 1245/BD-I 30/07/2024 60 M.K.CONSTRUCTION 22.29 0.00 0 0
4 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Augmentation of BANSGARA ZONE-I Piped water supply scheme to accommodate construction of OHR , laying of design pipeline and providing FHTC (Functional Household Tap Connection ) under Jal Jeevan Mission in Raninagar-II Block of Murshidabad District under Berhampore Division-I,PHE.Dte. Assistant Engineer Junior Engineer-I ORD/000142/2023-2024 628/BD-I 04/08/2023 310 SUNIL RABI DAS 388.80 70.77 18.2 5
5 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Repair And Renovation Works Of OHR (100 Cum) of Ground Water Based Supply Scheme for Bansgara Zone-I of Raninagar-II block under Berhampore Division-I PHEDte. in the district Murshidabad. Augmentation of PWSS under Jal jeevan Mission. Assistant Engineer Junior Engineer-II ORD/000248/2023-2024 1032/BD-I 01/11/2023 30 ALOK BANERJEE ENTERPRISE 6.83 0.00 0 80
6 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Route Survey ,Design of distribution network and Preparation of DPR for providing FHTC (Functional House Hold Tap Connection) by Augmentation under Jal Swapna for BANSGARA Water Supply Scheme of LALGOLA Block of Murshidabad District under Berhampore Division-I ,P.H.E Dte. Assistant Engineer-I JE ORD/000264/2022-2023 1687/BD-I 14/03/2023 10 ENVIROTECH SOLUTIONS 2.73 2.76 101.1 1
7 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Route Survey ,Design of distribution network and Preparation of DPR for providing FHTC (Functional House Hold Tap Connection) by Augmentation under Jal Swapna for BANSGARA ZONE-I Water Supply Scheme of RANINAGAR-II Block of Murshidabad District under Berhampore Division-I ,P.H.E Dte Assistant Engineer-I JE_Pravin Kumar Gupta ORD/000276/2022-2023 1759/BD-I 24/03/2023 10 M/S SOBHA & CO 2.60 2.60 100 100
8 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Material Requisition To Resource Division RTOR000011/2023-2024 61/BD-1/10 27/04/2023 Resource Division 30.97 0.00 0 0
9 MURSHIDABAD Berhampore Division I Augmentation of Ground Water Based Piped Water Supply Scheme for Bansgara Zone- I . , SM/14736 Augmentation Material Requisition To Resource Division RTOR000081/2023-2024 201/BD-1/22 10/02/2024 Resource Division 83.89 0.00 0 0
Total 1,267.33 76.13 6.01