Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 321.25 2.56 0.8  
1 MURSHIDABAD Murshidabad Division AUGMENTATION OF GROUND WATER BASED MURADPUR JALANGI ZONE-I IN JALANGI BLOCK WITHIN MURSHIDABAD DISTRICT UNDER MURSHIDABAD DIVISION, PHE DTE. , SM/14828 Augmentation Operation & Maintenance for Arsenic cum Iron Removal Plant of Muradpur Jalangi Zone-I PWSS( Capacity 54 m3/hr) Under Murshidabad Division P.H.E. Dte.for 12(Twelve) Months. (Period form i.e. 01/07/2024 to 30/06/2025) ASSISTANT ENGINEER JUNIOR ENGINEER 1 ORD/000036/2024-2025 1851/MURD 25/06/2024 360 TIPU CONSTRUCTION (PROP. SUJAUDDIN ) 8.51 0.00 0 0
2 MURSHIDABAD Murshidabad Division AUGMENTATION OF GROUND WATER BASED MURADPUR JALANGI ZONE-I IN JALANGI BLOCK WITHIN MURSHIDABAD DISTRICT UNDER MURSHIDABAD DIVISION, PHE DTE. , SM/14828 Augmentation Augmentation of MURADPUR JALANGI ZONE-I PWSS Laing Distribution System, Rising Main Connection Repairing P.H, B.W, Construction of P.H of JALANGI Block , under Murshidabad Division PHE. Dte. ASSISTANT ENGINEER ORD/000531/2023-2024 3114/MURD 05/10/2023 180 ARINDAM MAJUMDAR 187.44 0.00 0 0
3 MURSHIDABAD Murshidabad Division AUGMENTATION OF GROUND WATER BASED MURADPUR JALANGI ZONE-I IN JALANGI BLOCK WITHIN MURSHIDABAD DISTRICT UNDER MURSHIDABAD DIVISION, PHE DTE. , SM/14828 Augmentation Refilling of sand layers, Activated Alumina & existing gravel after washing along with allied works of AIRP at Saikhpara Area (Capacity 100 Cum/hr.) & Muradpur Jalangi Z-I (Capacity 54.00 Cum/hr.) Water Supply Scheme under Islampur Sub-Division under Murshidabad Division, PHE Dte. ASSISTANT ENGINEER JUNIOR ENGINEER 1 ORD/000842/2023-2024 820/MURD 15/03/2024 60 M/S. S. DAS AND ENTERPRISE 70.68 0.00 0 0
4 MURSHIDABAD Murshidabad Division AUGMENTATION OF GROUND WATER BASED MURADPUR JALANGI ZONE-I IN JALANGI BLOCK WITHIN MURSHIDABAD DISTRICT UNDER MURSHIDABAD DIVISION, PHE DTE. , SM/14828 Augmentation Preparation of D.P.R Consultancy work ( Augmentation/With Retrofitting/Retrofitting Only) in connection with the Functional House Hold Tap Connection of 06(SIX) Nos existing commissioned PWSS of Jalangi, Raninagar-I & Raninagar-II Block under Islampur Sub-Division Murshidabad Division P.H.E. Dte. PART-B ASSISTANT ENGINEER JUNIOR ENGINEER 1 ORD/001670/2021-2022 297/MURD 03/02/2022 60 SAI GEOMETRIC SOLUTION 28.62 2.56 8.94 100
5 MURSHIDABAD Murshidabad Division AUGMENTATION OF GROUND WATER BASED MURADPUR JALANGI ZONE-I IN JALANGI BLOCK WITHIN MURSHIDABAD DISTRICT UNDER MURSHIDABAD DIVISION, PHE DTE. , SM/14828 Augmentation Material Requisition To Resource Division RTOR000235/2023-2024 1219/MURD/15 03/05/2023 Resource Division 26.00 0.00 0 0
Total 321.25 2.56 0.8