Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 600.04 33.34 5.56  
1 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Sinking of Two nos 250mm. Dia. x 150mm. big dia. Tube Well of 150 Mtr. deep by Direct Rotary Rig method using UPVC (CM) Pipes & UPVC Medium Well Screen (RMS) Pipes with Ribs for Mobarakpur Piped Water supply scheme (Head Work Site & 2nd Tube well site) at Kaliachak-II Block under Malda Arsenic Area Water Supply Division , P.H.E. Dte., Malda Assistant Engineer-II Junior Engineer-II ORD/000128/2023-2024 1471/MAAD 01/08/2023 45 A ONE ENTERPRISE 14.79 0.00 0 100
2 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Construction of 3.6mtr.X 3.0mtr Switch Room cum chlorine room with Water Supply and sanitary arragement at 2nd Tube Well site of Mobarakpur Piped Water Supply Scheme under Malda Arsenic Area W/S Division, P.H.E.Dte. In the District of Malda Assistant Engineer-II Junior Engineer-II ORD/000130/2023-2024 1472/MAAD 01/08/2023 60 M/S EHAN ENTERPRISE 5.02 0.00 0 0
3 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Laying of Distribution System at Chowdhuri Tola for Mobarakpur Piped Water supply scheme at Kaliachak-II Block under Malda Arsenic Area W/S Division, P.H.E.Dte. In the District of Malda. Assistant Engineer-II Junior Engineer-II ORD/000131/2023-2024 1473/MAAD 01/08/2023 90 A. K. CONSTRUCTION 43.94 18.30 41.65 95
4 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Laying of Distribution System at Jahantola, Narasinghatola, Rabiramtola for Mobarakpur Piped Water supply scheme at Kaliachak-II Block under Malda Arsenic Area W/S Division, P.H.E.Dte. In the District of Malda. Assistant Engineer-II Junior Engineer-II ORD/000132/2023-2024 1474/MAAD 01/08/2023 90 GOBINDA ENTERPRISE 42.15 15.04 35.68 92
5 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Construction of Arsenic-cum-Iron Removal Plant (AIRP) for Mobarakpur Piped Water supply scheme at Kaliachak-II Block under Malda Arsenic Area W/S Division, P.H.E.Dte. in the District of Malda.(3rd Call) Assistant Engineer-II Junior Engineer-II ORD/000278/2023-2024 3080/MAAD 14/12/2023 365 M/S PARIMAL DAS 168.04 0.00 0 0
6 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Construction of 500 Cum capacity 20 Mtr. staging height RCC Over Head Reservoir as per Departmental Design & Drawing including pipe connection, Soil Investigation and Providing Functional House Hold Tap Connection (FHTC) for Mobarakpur Piped Water Supply scheme at Kaliachak-II Block under Malda Arsenic Area W/S Division, P.H.E. Dte, Malda. .(3rd Call) Assistant Engineer-II Junior Engineer-II ORD/000279/2023-2024 3081/MAAD 14/12/2023 270 M/S PARIMAL DAS 212.51 0.00 0 0
7 MALDAH Kaliachak - II Malda Ars Area W/S Division Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Material Requisition To Resource Division RTOR000010/2023-2024 633/MAAD 05/04/2023 Resource Division 42.92 0.00 0 0
8 MALDAH Kaliachak - II Malda Mechanical Mabarakpur Mouza Piped water supply Scheme of Kaliachak-II block under Malda Arsenic area water Supply Division, PHED , SM/17178 New Supply,delivery, installation and trial operation of Electro-Mechanical components and allied works at Ground Water Based Tubewell No-I & II and Arsenic Iron Removal Plant at Mabarakpur Piped Water Supply Scheme in the district of Malda Under Malda Mechanical Division, PHE Dte Assistant Engineer - II Junior Engineer-03 ORD/002481/2023-2024 97/MLMD 11/01/2024 180 HANNAN BUILDERS PVT. LTD. 70.67 0.00 0 0
Total 600.04 33.34 5.56