Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 23,924.69 0 0  
1 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) under command area of Paramanandapur, Biswambhar Binodpur, Bishnupur Shrirampara, Kamalpur, Paschim Narayanpur, Enayetpur and Gouripurr Zone Water Supply Scheme at Manikchak Block under Malda Arsenic Ar , SM/11917 Retrofitting Laying of CI/DI 200mm dia Pipe for overflow line & other allied works at Dharampur Distribution Zone of Northern sector under Malda Arsenic Area W/S Division, P.H.E. Dte, Malda. Assistant Engineer-I Junior Engineer-I ORD/000125/2024-2025 1256/MAAD 24/06/2024 15 ACHARYYA CONSTRUCTION 1.45 0.00 0 0
2 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) under command area of Paramanandapur, Biswambhar Binodpur, Bishnupur Shrirampara, Kamalpur, Paschim Narayanpur, Enayetpur and Gouripurr Zone Water Supply Scheme at Manikchak Block under Malda Arsenic Ar , SM/11917 Retrofitting Laying of clear water transmission main from existing WTPs (Mathurapur and Dariapur) to different zonal OHR sites of Manikchak and Kaliachak-III Block, construction of OHR on pile or raft foundation based on soil test report, laying of Distribution system and FHTC in Manikchak, Englishbazar, Kaliachak-I,II & III Blocks in the district of Malda. Assistant Engineer-I,Assistant Engineer-II Junior Engineer-I,Junior Engineer-II,Junior Engineer-III,Junior Engineer-IV ORD/000170/2023-2024 1524/MAAD 14/08/2023 540 ECO PROTECTION ENGINEERS PRIVATE LIMITED 23,923.24 0.00 0 20
Total 23,924.69 0.00 0