Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 24,041.38 3.9 0.02  
1 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) within the command area of Pardeonapur and its adjoining Mouzas in Kaliachak-III Block under Malda Arsenic Area Water Supply Division, PHE Dte. , SM/10430 Retrofitting Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) under command area of Godhan tola to Munnatola at Kumbhira Piped Water Supply Scheme at Kaliachak-III Block under Malda Arsenic Area Water Supply Division, PHE Dte. Assistant Engineer-II Junior Engineer-III ORD/000037/2023-2024 885/MAAD 11/05/2023 60 M/S AMIT KUMAR GUPTA 34.21 0.00 0 0
2 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) within the command area of Pardeonapur and its adjoining Mouzas in Kaliachak-III Block under Malda Arsenic Area Water Supply Division, PHE Dte. , SM/10430 Retrofitting Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SWAPNA) under command area of Alinagar Water Supply Scheme (Mouza- Nabinagar) at Kaliachak-I Block under Malda Arsenic Area Water Supply Division, PHE Dte. Assistant Engineer-II Junior Engineer-II ORD/000112/2022-2023 1014/MAAD 12/05/2022 60 M/S ALISA CONSTRUCTION 82.20 0.00 0 15
3 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) within the command area of Pardeonapur and its adjoining Mouzas in Kaliachak-III Block under Malda Arsenic Area Water Supply Division, PHE Dte. , SM/10430 Retrofitting Laying of clear water transmission main from existing WTPs (Mathurapur and Dariapur) to different zonal OHR sites of Manikchak and Kaliachak-III Block, construction of OHR on pile or raft foundation based on soil test report, laying of Distribution system and FHTC in Manikchak, Englishbazar, Kaliachak-I,II & III Blocks in the district of Malda. Assistant Engineer-I,Assistant Engineer-II Junior Engineer-I,Junior Engineer-II,Junior Engineer-III,Junior Engineer-IV ORD/000170/2023-2024 1524/MAAD 14/08/2023 540 ECO PROTECTION ENGINEERS PRIVATE LIMITED 23,923.24 0.00 0 20
4 MALDAH Malda Ars Area W/S Division Providing Functional Household Tap Connection (FHTC) within the command area of Pardeonapur and its adjoining Mouzas in Kaliachak-III Block under Malda Arsenic Area Water Supply Division, PHE Dte. , SM/10430 Retrofitting Continuation Work Order for Placing of diesel driven Car on hire basis for official use of the Executive Engineer, Malda Arsenic Area W/S Division, PHE Dte. under Malda Arsenic Area W/S Division, PHE Dte.(for the period from 01.01.2023 to 31.12.2023)= 365 days Assistant Engineer-I Junior Engineer-I ORD/000404/2022-2023 2330/MAAD 28/12/2022 365 NITAI PANDEY 1.73 3.90 225.43 25
Total 24,041.38 3.90 0.02