Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 1,134.5 313.82 27.66  
1 MALDAH Gazole Malda Division PARAHAR PWSS , SM/18432 New Construction of Boundary Wall at 2nd Tube Well site of Parahar Water Supply Scheme under Gazole Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000181/2024-2025 2956/MD 10/06/2024 30 HANNAN BUILDERS PVT. LTD. 7.92 0.00 0 0
2 MALDAH Gazole Malda Division PARAHAR PWSS , SM/18432 New Construction of Boundary Wall at Head Work site of Parahar Water Supply Scheme under Gazole Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000270/2024-2025 3228/MD 28/06/2024 30 HANNAN BUILDERS PVT. LTD. 27.72 0.00 0 0
3 MALDAH Gazole Malda Division PARAHAR PWSS , SM/18432 New Formal work order for the work of Implementation of PARAHAR Piped Water Supply Scheme at Gazole Dev. Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000316/2023-2024 2951/MD 02/08/2023 270 HANNAN BUILDERS PVT. LTD. 1,038.77 313.82 30.21 30
4 MALDAH Gazole Malda Division PARAHAR PWSS , SM/18432 New Material Requisition To Resource Division RTOR000192/2023-2024 814/MD 21/02/2024 Resource Division 47.82 0.00 0 0
5 MALDAH Gazole Malda Mechanical PARAHAR PWSS , SM/18432 New W.B.S.E.D.C.LTD Quotation charge at TW No- II of Parahar, Pandua CCC in the dist of Malda Under Malda Mechanical Division PHE Dte. BILL/03696/2023-2024 BP-2023-24-674 11/03/2024 W.B.S.E.D.C.LTD 5.86 0.00 0 null
6 MALDAH Gazole Malda Mechanical PARAHAR PWSS , SM/18432 New W.B.S.E.D.C.LTD Quotation charge at TW No- I of Parahar, Pandua CCC in the dist of Malda Under Malda Mechanical Division PHE Dte. BILL/03697/2023-2024 BP-2023-24-675 11/03/2024 W.B.S.E.D.C.LTD 6.41 0.00 0 null
Total 1,134.50 313.82 27.66