Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 204.47 | 46.54 | 22.76 | ||||||||||||||
1 | MALDAH | Malda Division | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Formal work order for the work of Augmentation of BHINGOLE Piped Water Supply Scheme at Harishchandrapur-I Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Tilok Roy, Junior Engineer | ORD/000084/2023-2024 | 2321/MD | 08/06/2023 | 365 | M/S. TEWARI CONSTRUCTION | 123.04 | 44.33 | 36.03 | 80 | |
2 | MALDAH | Malda Division | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Construction of Boundary Wall at Head Work site of Bhingole Water Supply Scheme under Harishchandrapur-I Block under Malda Division, PHE Dte. in the district of Malda. | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Tilok Roy, Junior Engineer | ORD/000300/2024-2025 | 3446/MD | 11/07/2024 | 30 | M/S TEWARI CONSTRUCTION | 37.37 | 0.00 | 0 | 0 | |
3 | MALDAH | Malda Division | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Material Requisition To Resource Division | RTOR000021/2023-2024 | 1610/MD | 11/04/2023 | Resource Division | 4.52 | 0.00 | 0 | 0 | ||||
4 | MALDAH | Malda Division | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Material Requisition To Resource Division | RTOR000083/2023-2024 | 1811/MD | 27/04/2023 | Resource Division | 8.78 | 0.00 | 0 | 0 | ||||
5 | MALDAH | Malda Mechanical | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | New service connection at BHINGOL T/W NO IV Under EE/MLMD PHE DTE DIST. Malda.( Harishchandrapur c c c) | BILL/00768/2024-2025 | BP-2024-25-189 | 22/05/2024 | W.B.S.E.D.C.LTD | 3.65 | 0.00 | 0 | null | ||||
6 | MALDAH | Malda Mechanical | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no.II & IV and making compound lighting arrangement at H/W site Augumentation of Bhingal Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/017675) | Assistant Engineer - II | ORD/000637/2023-2024 | 2736/MLMD | 14/08/2023 | 180 | SHREE BISHNU CONSTRUCTION | 22.69 | 0.00 | 0 | 0 | ||
7 | MALDAH | Malda Mechanical | AUGMENTATION OF BHINGOL PIPED WATER SUPPLY SCHEME , SM/15948 | Augmentation | Supply, installation & commissioning of electro-mechanical components at T/W no. I, Augmentation of Bhingal Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/017675) | Assistant Engineer - II | Junior Engineer-05 | ORD/000701/2023-2024 | 2722/MLMD | 14/08/2023 | 180 | CHOWDHURY CONCERN | 4.42 | 2.21 | 50 | 100 | |
Total | 204.47 | 46.54 | 22.76 |