Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 282.45 89.03 31.52  
1 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Construction of Boundary Wall at Head Work site of Aiho Zone-II Water Supply Scheme under Habibpur Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000299/2024-2025 3445/MD 11/07/2024 30 FUTURE 22.09 0.00 0 0
2 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Acceptance cum formal work order for Laying of Distribution system for Augmentation of AIHO ZONE-II Piped Water Supply Scheme at Habibpur Dev. Block of Malda District under Malda Division, PHE Dte., Govt. of West Bengal. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000555/2022-2023 1180/MD 21/03/2023 45 FUTURE 81.51 51.90 63.67 34
3 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Construction of 150 cum capacity 20 mtr. Staging height RCC OHR and Providing Household Tap Connection (FHTC) for Augmentation of AIHO ZONE-II Piped Water Supply Scheme at Habibpur Block of Malda District under Malda Division, PHE Dte, Govt. of West Bengal. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000703/2023-2024 4589/MD 22/11/2023 180 FUTURE 90.61 20.19 22.28 60
4 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Acceptance cum formal work order for Laying of Rising main and Construction of Pump houses for Augmentation of AIHO ZONE-II Piped Water Supply Scheme at Habibpur Block of Malda District under Malda Division, PHE Dte, Govt. of West Bengal. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000767/2022-2023 1396/MD 28/03/2023 45 UNITED FRIENDS UNEMPLOYED ENGG CO-OPE SOCEITY LTD 13.01 0.00 0 0
5 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) at AIHO ZONE-2 Water Supply Scheme under Habibpur Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000985/2023-2024 980/MD 04/03/2024 45 FUTURE 32.22 0.00 0 0
6 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Continuation work order for the work of Hiring of inspection Vehicle (Non-Air Condition, Bharat Stage-III on or after 01/05/2008 with Diesel/LPG/CNG Engine) in perfect good condition of performing a very long journey and should be covered anywhere without any trouble on monthly hire basis for Official use of the office of the Executive Engineer, Malda Division, PHE Dte. (Period from 01/05/2024 to 30/06/2024). Mr. Prasanta Mandal, Assistant Engineer,Mr. Prosanta Mandal, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer ORD/001218/2023-2024 1440/MD 15/03/2024 61 SHABNAM ARA 0.29 0.79 272.41 100
7 MALDAH Malda Division AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Material Requisition To Resource Division RTOR000084/2023-2024 1811/MD 27/04/2023 Resource Division 11.34 0.00 0 0
8 MALDAH Malda Mechanical AUMENTATION OF AIHO ZONE-II PIPED WATER SUPPLY SCHEME , SM/15188 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I,II & IV and making compund lighting arrangement at Head Work site of Augmentation of Aiho(zone-II) Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte.(TSM/017677) Assistant Engineer - II Junior Engineer-03 ORD/000585/2023-2024 2634/MLMD 10/08/2023 180 MAA BHABOTARINE ENTERPRISE. 31.38 16.15 51.47 15
Total 282.44 89.05 31.53