Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 29.44 8.42 28.6  
1 MALDAH Malda Division Source Augmentation of Bihari Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15083 Augmentation Acceptance cum formal work order for Laying of Distribution pipe line for Functional Household Tap Connection in connection with Jal Jeevan Mission (JJM and JAL SWAPNA ) under command area of Rampur village of Bihari Water Supply Scheme under Malda Division PHE. Dte in The District of Malda. Mr. Sumit Kumar Ghosh, Assistant Engineer Tapan Haldar, Junior Engineer ORD/000558/2022-2023 749/MD 17/02/2023 30 M/S. NAYAMEE ENGINEERING & CONSTRUCTIONS 5.67 5.35 94.36 100
2 MALDAH Malda Division Source Augmentation of Bihari Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15083 Augmentation Acceptance cum formal work order for Construction of 3.60 mtr.X 3.00 mtr Switch Room cum chlorine room with Water Supply and sanitary arrangement in connection with source Augmentation of Bihari Piped Water Supply Scheme at Ratua-I Block of Malda District under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Tapan Haldar, Junior Engineer ORD/000721/2022-2023 1195/MD 21/03/2023 45 M/S MAJAF CONSTRUCTION 4.17 0.00 0 0
3 MALDAH Malda Division Source Augmentation of Bihari Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15083 Augmentation Acceptance cum formal work order for Sinking of 01(one) nos. 250mm. Dia. x 150mm. Big dia Tube Well 138 Mtr. deep by D.R. Rig method using UPVC pipe & Strainer in connection with Source Augmentation of BIHARI Piped Water Supply Scheme under Malda Division P.H.E Dte in the District of Malda. (2nd Call) Mr. Sumit Kumar Ghosh, Assistant Engineer Tapan Haldar, Junior Engineer ORD/000776/2022-2023 1434/MD 29/03/2023 30 ABHIJIT PAUL 8.68 0.00 0 0
4 MALDAH Malda Mechanical Source Augmentation of Bihari Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15083 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components of T/W no. III of Behari Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/016679) Assistant Engineer - II Junior Engineer-05 ORD/000566/2023-2024 2618/MLMD 10/08/2023 180 NEOGI ENTERPRISE. 10.92 3.07 28.11 56
Total 29.43 8.41 28.58