Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 1,322.27 29.81 2.25  
1 MALDAH Malda Division Augmentation of Baharal Zone-I & II Piped Water Supply Scheme , SM/14099 Augmentation Formal work order for the work of Augmentation of BAHARAL ZONE-I and II Piped Water Supply Scheme at Ratua-I Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. Mr. Prosanta Mandal, Assistant Engineer Rahul Das Biswas, Junior Engineer ORD/000362/2023-2024 3067/MD 09/08/2023 270 GHOSH BROTHERS 1,160.22 0.00 0 3
2 MALDAH Malda Division Augmentation of Baharal Zone-I & II Piped Water Supply Scheme , SM/14099 Augmentation Acceptance cum formal work order for Route survey, design and preparation of DPR of Baharal Piped Water Supply Scheme at Ratua-I Dev. Block under Malda Division, PHE Dte. Mr. Prosanta Mandal, Assistant Engineer Mr. Sanjit Sarkar, Junior Engineer ORD/000685/2021-2022 650/MD 22/03/2022 15 ENVIROTECH SOLUTIONS 4.59 4.59 100 100
3 MALDAH Malda Division Augmentation of Baharal Zone-I & II Piped Water Supply Scheme , SM/14099 Augmentation Material Requisition To Resource Division RTOR000071/2023-2024 1811/MD 27/04/2023 Resource Division 90.88 0.00 0 0
4 MALDAH Malda Mechanical Augmentation of Baharal Zone-I & II Piped Water Supply Scheme , SM/14099 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I,II & III and making compound lighting arrangement at Head worksite of Baharal (zone-I) Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/011899) Assistant Engineer - II Junior Engineer-05 ORD/000509/2023-2024 2581/MLMD 04/08/2023 120 MERCURY ENGINEERING COMPANY. 33.22 12.61 37.96 76
5 MALDAH Malda Mechanical Augmentation of Baharal Zone-I & II Piped Water Supply Scheme , SM/14099 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I,II & III and making compound lighting arrangement at Head worksite of Baharal (zone-II) Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/011899) Assistant Engineer - II Junior Engineer-05 ORD/000510/2023-2024 2582/MLMD 04/08/2023 120 ANIMA ENTERPRISE 33.36 12.61 37.8 76
Total 1,322.27 29.80 2.25