Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 729.77 | 236.92 | 32.47 | ||||||||||||||
1 | MALDAH | Gazole | Malda Division | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | Formal work order for the work of Implementation of SAIDPUR Water Supply Scheme at Gazole Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. | Mr. Arnab Giri, Assistant Engineer | Amit Karmakar, Junior Engineer | ORD/000118/2023-2024 | 2320/MD | 08/06/2023 | 270 | NEOGI ENTERPRISE | 651.25 | 210.71 | 32.35 | 50 |
2 | MALDAH | Gazole | Malda Division | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | Construction of Boundary Wall at 2nd Tube Well site of Saidpur Water Supply Scheme under Gazole Block under Malda Division, PHE Dte. in the district of Malda. | Mr. Arnab Giri, Assistant Engineer | Amit Karmakar, Junior Engineer | ORD/000182/2024-2025 | 2957/MD | 10/06/2024 | 30 | SAYEM ENTERPRISE | 7.16 | 0.00 | 0 | 0 |
3 | MALDAH | Gazole | Malda Division | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | Material Requisition To Resource Division | RTOR000048/2023-2024 | 1811/MD | 27/04/2023 | Resource Division | 20.10 | 0.00 | 0 | 0 | |||
4 | MALDAH | Gazole | Malda Division | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | Material Requisition To Resource Division | RTOR000158/2023-2024 | 240/MD | 10/01/2024 | Resource Division | 12.66 | 0.00 | 0 | 0 | |||
5 | MALDAH | Gazole | Malda Mechanical | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | Supply, installation, commissioning and trial operation of electro-mechanical components of T/W no. I & II and making compound lighting arrangement at T/W no. I of Saidpur Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/014263) | Assistant Engineer - II | Junior Engineer-07 | ORD/000491/2023-2024 | 2563/MLMD | 04/08/2023 | 120 | SUBRATA SAHA | 28.62 | 16.23 | 56.71 | 78 |
6 | MALDAH | Gazole | Malda Mechanical | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | W.B.S.E.D.C.LTD Quotation charge at T/W No. I of Saidpur PWSS , Gazol C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. | Assistant Engineer - II | Junior Engineer-07 | ORD/001897/2023-2024 | 3004467185 | 17/10/2023 | 90 | W.B.S.E.D.C.LTD | 3.87 | 3.87 | 100 | 100 |
7 | MALDAH | Gazole | Malda Mechanical | SAIDPUR Piped Water Supply Scheme , SM/12766 | New | W.B.S.E.D.C.LTD Quotation charge at T/W No. II of Saidpur PWSS , Gazol C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. | Assistant Engineer - II | Junior Engineer-07 | ORD/001898/2023-2024 | 3004467024 | 17/10/2023 | 90 | W.B.S.E.D.C.LTD | 6.11 | 6.11 | 100 | 100 |
Total | 729.78 | 236.93 | 32.47 |