Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 267.64 50.76 18.97  
1 MALDAH Harischandrapur - II Malda Division DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Construction of Boundary Wall at 2nd Tube Well site of Dakshin Bhakuria Water Supply Scheme under Harishchandrapur-II Block under Malda Division, PHE Dte. in the district of Malda. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Susanta Pal, JE_Deputation ORD/000185/2024-2025 2960/MD 10/06/2024 30 SK ENTERPRISE 6.46 0.00 0 0
2 MALDAH Harischandrapur - II Malda Division DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Formal work order for the work of Implementation of DAKSHIN BHAKURIA Piped Water Supply Scheme at Harishchandrapur-I Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Susanta Pal, JE_Deputation ORD/000234/2023-2024 2707/MD 14/07/2023 270 MOTI RAHAMAN 202.31 42.30 20.91 35
3 MALDAH Harischandrapur - II Malda Division DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Acceptance cum formal work order for Sinking of 250mm. Dia. x 150 mm. Big dia. and 135 Mtr. deep Tube Well Drilling by Direct Rotary method with 150 mm dia upvc strainer of 30m length all complete including cost of materials at Heads Work Site of UTTAR BHAKURIA Piped Water Supply Scheme at Harishchandrapur-II Block of Malda District under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Susanta Pal, JE_Deputation ORD/000366/2022-2023 2695/MD 17/11/2022 30 ASHIS CONSTRUCTION 9.20 0.00 0 80
4 MALDAH Harischandrapur - II Malda Division DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Material Requisition To Resource Division RTOR000078/2023-2024 1811/MD 27/04/2023 Resource Division 9.78 0.00 0 0
5 MALDAH Harischandrapur - II Malda Division DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Material Requisition To Resource Division RTOR000135/2023-2024 114/MD 05/01/2024 Resource Division 3.70 0.00 0 0
6 MALDAH Harischandrapur - II Malda Mechanical DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New New service connection at Dakshin Bhakuria ph II PWSS T/W NO II Under EE/MLMD PHE DTE DIST. Malda.( Bhaluka c c c) BILL/00757/2024-2025 BP-2024-25-205 22/05/2024 W.B.S.E.D.C.LTD 4.70 0.00 0 null
7 MALDAH Harischandrapur - II Malda Mechanical DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New W.B.S.E.D.C.LTD Quotation charge at T/W No. I of DAKSHIN BHAKURIA, Bhaluka C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. BILL/02462/2023-2024 BP-2023-24-413 03/01/2024 W.B.S.E.D.C.LTD 5.87 0.00 0 0
8 MALDAH Harischandrapur - II Malda Mechanical DAKSHIN BHAKURIA Piped Water Supply Scheme , SM/12186 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I ,II and making compound lighting arrangement at T/W no. I of Dakshin Bhakuria Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/013248) Assistant Engineer - II Junior Engineer-05 ORD/000314/2023-2024 2315/MLMD 26/07/2023 120 DAS CONSTRUCTION 25.62 8.46 33.02 66
Total 267.64 50.76 18.97