Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 578.14 382.35 66.13  
1 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(100 nos) of Harishchandrapur-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10388 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Mahendrapur & Bhingole GP of Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Sanjit Sarkar, Junior Engineer ORD/000460/2022-2023 43/MD 16/01/2023 60 MILLENNIUM ENTERPRISR 97.04 84.30 86.87 80
2 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(100 nos) of Harishchandrapur-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10388 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Harishchandrapur & Boroi GP of Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Sanjit Sarkar, Junior Engineer ORD/000499/2022-2023 90/MD 17/01/2023 75 MAMATA USHA ENTERPRISE 188.85 178.19 94.36 97
3 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(100 nos) of Harishchandrapur-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10388 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Tulshihata GP of Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Sanjit Sarkar, Junior Engineer ORD/000507/2022-2023 198/MD 19/01/2023 75 MILLENNIUM ENTERPRISR 97.04 82.33 84.84 80
4 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(100 nos) of Harishchandrapur-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10388 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Rashidabad & Kushida GP of Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Sanjit Sarkar, Junior Engineer ORD/000580/2022-2023 817/MD 20/02/2023 75 NEOGI ENTERPRISE 129.47 37.53 28.99 95
5 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(100 nos) of Harishchandrapur-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10388 School Material Requisition To Resource Division RTOR000026/2021-2022 721/MD 25/03/2022 Resource Division 65.74 0.00 0 0
Total 578.14 382.35 66.14