Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 617.51 303.72 49.18  
1 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(87 nos) of Ratua-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10385 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Bilaimari & Mahanandatala GP of Ratua-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Tilok Roy, Junior Engineer,Tapan Haldar, Junior Engineer ORD/000422/2022-2023 3193/MD 27/12/2022 75 WATER TECH 157.20 124.67 79.31 63
2 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(87 nos) of Ratua-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10385 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for School at Debipur, Kahala & Baharal GP of Ratua-I Dev. Block under Malda Division, PHE Dte. Mr. Prosanta Mandal, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer ORD/000428/2022-2023 3199/MD 27/12/2022 75 USHA ENTERPRISE 129.85 94.81 73.02 100
3 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(87 nos) of Ratua-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10385 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Bhado, Ratua & Samsi GP of Ratua-I Dev. Block under Malda Division, PHE Dte. Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Tilok Roy, Junior Engineer,Tapan Haldar, Junior Engineer ORD/000505/2022-2023 102/MD 18/01/2023 75 MILLENNIUM ENTERPRISR 136.58 0.00 0 0
4 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(87 nos) of Ratua-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10385 School Formal work order for the work of Installation of Stand-Alone Community Purification Plant (CWPP) for Schools at Chandmani-I & Chandmani-II GP of Rtua-I Dev. Block under Malda Division, PHE Dte. Mr. Prasanta Mandal, Assistant Engineer,Mr. Sumit Kumar Ghosh, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer,Mr. Tilok Roy, Junior Engineer,Tapan Haldar, Junior Engineer ORD/000515/2022-2023 468/MD 07/02/2023 75 MILLENNIUM ENTERPRISR 136.58 84.24 61.68 100
5 MALDAH Malda Division Installation of Stand-Alone Community Purification Plant at Schools(87 nos) of Ratua-I Dev. Block, Malda under Malda Division, PHE Dte. , SM/10385 School Material Requisition To Resource Division RTOR000024/2021-2022 719/MD 25/03/2022 Resource Division 57.30 0.00 0 0
Total 617.50 303.72 49.18