Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 747.73 123.28 16.49  
1 DAKSHIN DINAJPUR Balurghat Division Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Urgent restoration of Shoulder in stretches for laying of Drinking water supply pipeline along PWD(Roads) for Daulatpur-Harirampur-Dehaband Road from (chainage 7.00 K.M to 20.60 K.M). BILL/00193/2024-2025 BP-2024-25-124 10/09/2024 EXECUTIVE ENGINEER, DAKSHIN DINAJPUR, HIGHWAY DIVISION, P.W.(ROADS) DTE. 17.47 0.00 0 null
2 DAKSHIN DINAJPUR Balurghat Division Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Urgent restoration of Shoulder in stretches for laying of Drinking water supply pipeline along PWD(Roads) for Harirampur-Beldangi Road from (Chainage 0.0 K.M to 9.40 K.M). BILL/00210/2024-2025 null 11/09/2024 EXECUTIVE ENGINEER, DAKSHIN DINAJPUR, HIGHWAY DIVISION, P.W.(ROADS) DTE. 19.58 0.00 0 null
3 DAKSHIN DINAJPUR Balurghat Division Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Sinking of Tubewell, Laying of Rising Main & Distribution System, Providing FHTC, Construction of 400 Cum capacity OHR with 20m Staging Height including with Soil Investigation, Pump House, Boundary Wall & Approach Road for Augmentation of Harirampur Piped Water Supply Scheme at Harirampur Block in the District of DakshinDinajpur under Balurghat Division, PHE Dte. Assistant Engineer Sadar Junior Engineer 2 ORD/000091/2023-2024 991/BD 31/07/2023 300 ASHIT KUMAR DEBSHARMA 635.33 113.66 17.89 40
4 DAKSHIN DINAJPUR Balurghat Division Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Material Requisition To Resource Division RTOR000049/2023-2024 38/BD 09/01/2024 Resource Division 12.81 0.00 0 0
5 DAKSHIN DINAJPUR Balurghat Division Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Material Requisition To Resource Division RTOR000074/2022-2023 3493/BD 03/03/2023 Resource Division 37.69 0.00 0 0
6 DAKSHIN DINAJPUR Malda Mechanical Augmentation of Ground Water Based Harirampur Piped Water Supply Scheme , SM/12798 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II, making compound lighting arrangement at T/W no. I of Augmentation of Harirampur Water Supply Scheme in the District of Dakshin Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/014718) Assistant Engineer - I Junior Engineer-01 ORD/000459/2023-2024 2552/MLMD 04/08/2023 120 MANIK CHANDRA SAHA. 24.85 9.62 38.71 78
Total 747.73 123.28 16.49