Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 744.27 9.76 1.31  
1 DAKSHIN DINAJPUR Bansihari Balurghat Division DILKUNTHI Piped Water Supply Scheme at Bansihari Block , SM/12063 New Sinking of Tubewell, Laying of Rising Main & Distribution System, Providing FHTC, Construction of 350 Cum capacity OHR with 20m Staging Height including with Soil Investigation, Pump House for implementation of Dilkunthi Piped Water Supply Scheme at Banshihari Block in the District of Dakshin Dinajpur under Balurghat Division, PHE Dte. Assistant Engineer Sadar Junior Engineer (Civil) ORD/000029/2023-2024 370/BD 22/05/2023 300 M/S. NANDY ENTERPRISE 689.75 0.00 0 10
2 DAKSHIN DINAJPUR Bansihari Balurghat Division DILKUNTHI Piped Water Supply Scheme at Bansihari Block , SM/12063 New Material Requisition To Resource Division RTOR000058/2022-2023 2879/BD 06/01/2023 Resource Division 19.30 0.00 0 0
3 DAKSHIN DINAJPUR Bansihari Malda Mechanical DILKUNTHI Piped Water Supply Scheme at Bansihari Block , SM/12063 New W.B.S.E.D.C.LTD Quotation charge at P/H No. I of DILKUNTHI, Buniadpur C.C.C in the district of Dakshin Dinajpur Under Malda Mechanical Division PHE Dte. BILL/02563/2023-2024 BP-2023-24-458 17/01/2024 W.B.S.E.D.C.LTD 3.02 0.00 0 0
4 DAKSHIN DINAJPUR Bansihari Malda Mechanical DILKUNTHI Piped Water Supply Scheme at Bansihari Block , SM/12063 New W.B.S.E.D.C.LTD Quotation charge at P/H No. II of DILKUNTHI, Buniadpur C.C.C in the district of Dakshin Dinajpur Under Malda Mechanical Division PHE Dte. BILL/02564/2023-2024 BP-2023-24-459 17/01/2024 W.B.S.E.D.C.LTD 5.35 0.00 0 0
5 DAKSHIN DINAJPUR Bansihari Malda Mechanical DILKUNTHI Piped Water Supply Scheme at Bansihari Block , SM/12063 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I ,II and making compound lighting arrangement at T/W no. I of Dilkunthi Water Supply Scheme in the District of Dakshin Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/013332) Assistant Engineer - I Junior Engineer-01 ORD/000351/2023-2024 2341/MLMD 26/07/2023 120 ANIMA ENTERPRISE 26.85 9.76 36.35 65
Total 744.28 9.76 1.31