Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
5 | 77.27 | 0 | 0 | ||||||||||||||
1 | UTTAR DINAJPUR | Raiganj Division | Source Augmentation for Pokheria Piped Water Suppply Scheme under Goalpokhar-I block in the district of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. , SM/14226 | Augmentation | Construction of Boundary Wall Laying Distribution, Providing FHTC, Pump House in connection with Source Augmentation of Pokheria Piped Water Supply Scheme of Goalpokhar-I Block in the District of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. | Assistant Engineer ISD | Junior Engineer, ISD | ORD/000194/2022-2023 | 62/RD/PHE | 16/01/2023 | 45 | RAHUL ENTERPRISE RNJRAHULENTERPRISE@GMAIL.COM | 17.78 | 0.00 | 0 | 0 | |
2 | UTTAR DINAJPUR | Raiganj Division | Source Augmentation for Pokheria Piped Water Suppply Scheme under Goalpokhar-I block in the district of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. , SM/14226 | Augmentation | Rig Bored Tube-Well in connection with Source Augmentation In Different Piped Water Supply Scheme 1.Mohua, 2. Pawakhali, 3. Pokheria in the District of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. | Assistant Engineer ISD | Junior Engineer, ISD | ORD/000278/2022-2023 | 471/RD/PHE | 16/02/2023 | 45 | M/S SARKAR ENTERPRISE SILIGURI | 31.92 | 0.00 | 0 | 40 | |
3 | UTTAR DINAJPUR | Raiganj Division | Source Augmentation for Pokheria Piped Water Suppply Scheme under Goalpokhar-I block in the district of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. , SM/14226 | Augmentation | Material Requisition To Resource Division | RTOR000099/2023-2024 | 2399/RD/PHE | 17/08/2023 | Resource Division | 2.38 | 0.00 | 0 | 0 | ||||
4 | UTTAR DINAJPUR | Malda Mechanical | Source Augmentation for Pokheria Piped Water Suppply Scheme under Goalpokhar-I block in the district of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. , SM/14226 | Augmentation | Quotation for new service connection at Source Augmentation of POKHERIA PH-III (Goalpokher ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. | BILL/00228/2024-2025 | BP-2024-25-79 | 16/04/2024 | W.B.S.E.D.C.LTD | 14.28 | 0.00 | 0 | null | ||||
5 | UTTAR DINAJPUR | Malda Mechanical | Source Augmentation for Pokheria Piped Water Suppply Scheme under Goalpokhar-I block in the district of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. , SM/14226 | Augmentation | Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. III of Pokheria Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/016497) | ORD/002033/2023-2024 | 4771/MLMD | 29/12/2023 | 120 | ARATI ENGINEERING | 10.91 | 0.00 | 0 | 0 | |||
Total | 77.27 | 0.00 | 0 |