Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 48.87 20.99 42.95  
1 UTTAR DINAJPUR Raiganj Division Source Augmentation for Kotar Piped Water Supply Scheme under Itahar Block in the District of Uttar Dinajpur under Raiganj Division P.H.E. Dte. , SM/12651 Augmentation Source(Rig Bored Tube-Well) Augmentation of Kotar Piped Water Supply Scheme of Itahar Block in the District of Uttar Dinajpur under Raiganj Division, P.H.E. Dte. Assistant Engineer RSD Junior Engineer, RSD ORD/000124/2022-2023 1908/RD/PHE 28/10/2022 45 M/S SARKAR ENTERPRISE (ABDULGHATA) MSSARKAR.RNJ@GMAIL.COM 32.51 15.04 46.26 30
2 UTTAR DINAJPUR Raiganj Division Source Augmentation for Kotar Piped Water Supply Scheme under Itahar Block in the District of Uttar Dinajpur under Raiganj Division P.H.E. Dte. , SM/12651 Augmentation Material Requisition To Resource Division RTOR000117/2023-2024 11/RD/PHE 03/01/2024 Resource Division 1.42 0.00 0 0
3 UTTAR DINAJPUR Malda Mechanical Source Augmentation for Kotar Piped Water Supply Scheme under Itahar Block in the District of Uttar Dinajpur under Raiganj Division P.H.E. Dte. , SM/12651 Augmentation Quotation for new service connection at Source Augmentation of KOTAR PH-III (Itahar ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/12651) BILL/01056/2024-2025 BP-2024-25-240 29/05/2024 W.B.S.E.D.C.LTD 4.39 0.00 0 null
4 UTTAR DINAJPUR Malda Mechanical Source Augmentation for Kotar Piped Water Supply Scheme under Itahar Block in the District of Uttar Dinajpur under Raiganj Division P.H.E. Dte. , SM/12651 Augmentation Supply, installation ,commissioning and trial operation of electro-mechanical components at T/W no. III of Source augmentation of Kotar Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/015244) Assistant Engineer - I Junior Engineer-02 ORD/000358/2023-2024 2369/MLMD 28/07/2023 120 SUBRATA KUMAR DAS. 10.55 5.95 56.4 87
Total 48.87 20.99 42.94