Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 895.23 389.21 43.48  
1 COOCHBEHAR Coochbehar Division REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Execution of different works related to BARA ATIABARI P KHANDA PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000061/2024-2025 1302/CD 06/06/2024 90 MS SSB CONSTRUCTION CO 86.73 0.00 0 0
2 COOCHBEHAR Coochbehar Division REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Execution of different works related to BARA ATIABARI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000110/2023-2024 663/CD 14/07/2023 150 MS SSB CONSTRUCTION CO 652.47 354.38 54.31 60
3 COOCHBEHAR Coochbehar Division REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Preparation of DPR for Augmentation of Bara Atiabari Piped Water Supply Scheme under Cooch Behar Sadar Sub-division of Cooch Behar Division,P.H.E.Dte. ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000302/2021-2022 1017/CD/W 10/01/2022 20 SAMARTH INFRA-TECH SERVICES PVT. LTD. 3.60 3.60 100 100
4 COOCHBEHAR Coochbehar Division REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Execution of different works related to B.ATIABARI P.KHANDA PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000507/2023-2024 304/CD 09/02/2024 60 MS SSB CONSTRUCTION CO 88.79 20.16 22.71 45
5 COOCHBEHAR Coochbehar Division REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Material Requisition To Resource Division RTOR000061/2023-2024 170/CD 27/04/2023 Resource Division 31.38 0.00 0 0
6 COOCHBEHAR Northern Mechanical Division II REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation New service connection at Bara atiabari PWSS, P/H-III BILL/02211/2023-2024 BP-2023-24-491 21/12/2023 WBSEDCL 4.41 0.00 0 0
7 COOCHBEHAR Northern Mechanical Division II REJUVENATION OF BARA ATIABARI PRATHAM KHANDA PIPED WATER SUPPLY SCHEME , SM/18299 Augmentation Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvination of Bara Atiabari Pratham Khanda water supply scheme, TW no I of Zone-I and TW no I and II of Zone-II under JJM under NMD-II, PHE Dte. APD. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 3, Cooch-Behar Mechanical Sub-Division, ORD/000863/2023-2024 2444/NMD-II 11/08/2023 30 GEETA CONSTRUCTION 27.85 11.07 39.75 40
Total 895.23 389.20 43.48