Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 295.48 43.77 14.81  
1 COOCHBEHAR Coochbehar Division AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation Execution of different works related to Aug. of CHAKCHAKA ZONE - II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 163/1-5/NBC-1; Dt.: 18-05-23 ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000010/2023-2024 395/CD 23/05/2023 150 SWAPAN KR.SARKAR 204.49 43.77 21.4 22
2 COOCHBEHAR Coochbehar Division AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation Execution of different works related to (within TAKAGACH area) CHAKCHAKA ZONE II PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000341/2023-2024 1325/CD 24/11/2023 60 SWAPAN KR.SARKAR 31.80 0.00 0 70
3 COOCHBEHAR Coochbehar Division AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation Laying DI P/Line & other allied works related to CHAKCHAKA PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000577/2023-2024 617/CD 11/03/2024 60 M/S. MANDAL CONSTRUCTION 14.77 0.00 0 30
4 COOCHBEHAR Coochbehar Division AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation Material Requisition To Resource Division RTOR000040/2023-2024 144/CD 27/04/2023 Resource Division 11.66 0.00 0 0
5 COOCHBEHAR Northern Mechanical Division II AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation NEW SERVICE CONNECTION AT CHAKCHAKA ZONE-II, PH-I BILL/02737/2023-2024 BP-2023-24-611 16/02/2024 WBSEDCL 5.38 0.00 0 null
6 COOCHBEHAR Northern Mechanical Division II AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation NEW SERVICE CONNECTION CHARGES AT CHAKCHAKA ZONE-II, PH-II BILL/02739/2023-2024 BP-2023-24-610 16/02/2024 WBSEDCL 6.31 0.00 0 null
7 COOCHBEHAR Northern Mechanical Division II AUGUMENTATION OF GROUND WATER BASED CHAKCHAKA ZONE II PWSS COOCHBEHAR II BLOCK WITHIN COOCHBEHAR DISTRICT UNDER COOCHBEHAR DIVISION , PHE DTE , SM/18093 Augmentation Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Chakchaka Water Supply Scheme TW No.-I and II of Zone-II under NMD-II,PHE.Dte,,Apd. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 2, Cooch-Behar Mechanical Sub-Division, ORD/001082/2023-2024 2779/NMD-II 05/10/2023 30 MUSTAFI CONCERN 21.07 0.00 0 80
Total 295.48 43.77 14.81