Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 304.39 | 82.59 | 27.13 | ||||||||||||||
1 | COOCHBEHAR | Dinhata - II | Coochbehar Division | Maidam Piped Water Supply Scheme , SM/16981 | New | Execution of different works related to AUG of MAIDAM PWSS under JAL JEEVAN MISSION . | ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION,ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION | JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION,JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION | ORD/000004/2023-2024 | 49/CD | 17/04/2023 | 150 | KHOKAN DAS | 200.29 | 74.97 | 37.43 | 95 |
2 | COOCHBEHAR | Dinhata - II | Coochbehar Division | Maidam Piped Water Supply Scheme , SM/16981 | New | Execution of different works related to MAIDAM PWSS under JAL JEEVAN MISSION | ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION | JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION | ORD/000515/2023-2024 | 313/CD | 09/02/2024 | 60 | KHOKAN DAS | 43.13 | 0.00 | 0 | 95 |
3 | COOCHBEHAR | Dinhata - II | Northern Mechanical Division II | Maidam Piped Water Supply Scheme , SM/16981 | New | New service connection at Maidam PWSS, P/H-I | BILL/02323/2023-2024 | BP-2023-24-540 | 17/01/2024 | WBSEDCL | 15.58 | 0.00 | 0 | 0 | |||
4 | COOCHBEHAR | Dinhata - II | Northern Mechanical Division II | Maidam Piped Water Supply Scheme , SM/16981 | New | New service connection at Maidam PWSS, P/H-II | BILL/02324/2023-2024 | BP-2023-24-541 | 17/01/2024 | WBSEDCL | 4.33 | 0.00 | 0 | 0 | |||
5 | COOCHBEHAR | Dinhata - II | Northern Mechanical Division II | Maidam Piped Water Supply Scheme , SM/16981 | New | QUOTATION FOR NSC AT MAIDAM TW NO II | BILL/02459/2023-2024 | null | 16/01/2024 | WBSEDCL | 4.33 | 0.00 | 0 | 0 | |||
6 | COOCHBEHAR | Dinhata - II | Northern Mechanical Division II | Maidam Piped Water Supply Scheme , SM/16981 | New | QUOTATION FOR NSC AT MAIDAM TW NO I | BILL/02460/2023-2024 | null | 16/01/2024 | WBSEDCL | 15.58 | 0.00 | 0 | 0 | |||
7 | COOCHBEHAR | Dinhata - II | Northern Mechanical Division II | Maidam Piped Water Supply Scheme , SM/16981 | New | Supply, delivery, installation, commissioning and trial run of electro-mechanical components alongwith Cu wound line voltage corrector for Rejuvenation of MAIDAM water supply scheme,TW no I AND II under JJM under NMD-II, PHE Dte.APD. | Assistant Engineer, Cooch-Behar Mechanical Sub-Division | Junior Engineer 3, Cooch-Behar Mechanical Sub-Division, | ORD/000940/2023-2024 | 2545/NMD-II | 16/08/2023 | 30 | M/S SAJAHAN CHOWDHURY | 21.15 | 7.62 | 36.03 | 50 |
Total | 304.40 | 82.59 | 27.13 |