Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 20,268.66 163.08 0.8  
1 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation FUEL BILL BILL/02031/2023-2024 null 01/03/2024 A.O BSNL 2.07 0.00 0 0
2 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation FUEL BILL BILL/02079/2023-2024 BP-1420 31/03/2024 R.C BANIK BANIK & SONS 2.07 0.00 0 0
3 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Execution of different works related to TUTIARKUTHI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000060/2024-2025 1309/CD 16/07/2024 90 MS SSB CONSTRUCTION CO 90.43 0.00 0 30
4 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Execution of different works related to Aug. of TUTIARKUTHI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION,ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION,JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000087/2023-2024 622/CD 12/07/2023 150 MS SSB CONSTRUCTION CO 288.61 123.47 42.78 38
5 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Laying of DI line along both the flanks of Roads in Cooch Behar District under Cooch Behar Division PHE Dte. CONTRACTUAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000339/2024-2025 1264/CD 02/07/2024 300 MACKINTOSH BURN LIMITED 19,789.29 0.00 0 0
6 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Providing FHTC & other allied works at TUTIARKUTHI ZI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000362/2022-2023 1015/CD 29/09/2022 30 SHYAMAL NATH 9.98 9.93 99.5 1
7 COOCHBEHAR Coochbehar Division Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Execution of different works related to TUTIARKUTHI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000394/2023-2024 1366/CD 05/12/2023 60 MS SSB CONSTRUCTION CO 68.30 29.68 43.46 78
8 COOCHBEHAR Northern Mechanical Division II Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Charges for new service connection at Tutiar kuthi PWSS, P/H-III in the dist of Coochbehar. BILL/01035/2024-2025 BP-305/24-25 22/08/2024 WBSEDCL 7.02 0.00 0 null
9 COOCHBEHAR Northern Mechanical Division II Augmentation of Tutiarkuthi Piped Water Supply Scheme. , SM/15930 Augmentation Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Tutiarkuthi Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,,Apd. ORD/001204/2023-2024 2950/NMD-II 10/11/2023 30 TAPAN BISWAS 10.89 0.00 0 0
Total 20,268.65 163.08 0.8