Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 20,279.26 252.71 1.25  
1 COOCHBEHAR Sitai Coochbehar Division BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New Laying of DI line along both the flanks of Roads in Cooch Behar District under Cooch Behar Division PHE Dte. CONTRACTUAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000339/2024-2025 1264/CD 02/07/2024 300 MACKINTOSH BURN LIMITED 19,789.29 0.00 0 0
2 COOCHBEHAR Sitai Coochbehar Division BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New Execution of different works related to CHHOTO GAROLJHORA PWSS under JAL JEEVAN MISSION ORD/000482/2023-2024 284/CD 09/02/2024 60 S.G ENTERPRISE 38.53 0.00 0 0
3 COOCHBEHAR Sitai Coochbehar Division BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New Execution of different works related to BARA ADABARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1176/1-5/NBC-1; Dt.: 24-02-23 ADDITIONAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, COOCH BEHAR DIVISION,JUNIOR ENGINEER, COOCHBEHAR DIVISION ORD/000574/2022-2023 1819/CD 06/03/2023 90 S.G ENTERPRISE 392.44 252.71 64.39 60
4 COOCHBEHAR Sitai Coochbehar Division BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New Material Requisition To Resource Division RTOR000033/2023-2024 142/CD 27/04/2023 Resource Division 28.05 0.00 0 0
5 COOCHBEHAR Sitai Northern Mechanical Division II BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New ELECTRIC QUOTATION BILL FOR NEW SERVICE CONNECTION AT BARA ADABARI TW NO. I BILL/02616/2023-2024 BP-2023-24-580 01/02/2024 WBSEDCL 4.37 0.00 0 null
6 COOCHBEHAR Sitai Northern Mechanical Division II BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New ELECTRIC QUOTATION BILL FOR NEW SERVICE CONNECTION AT BARA ADABARI TW II. BILL/02870/2023-2024 BP-2023-24-662 04/03/2024 WBSEDCL 5.13 0.00 0 null
7 COOCHBEHAR Sitai Northern Mechanical Division II BARA ADABARI PIPED WATER SUPPLY SCHEME , SM/14731 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bara Adabari water supply scheme, TW no I and II of under NMD-II, PHE Dte.APD ORD/000848/2023-2024 2420/NMD-II 10/08/2023 30 SUBODH KUMAR BANIK 21.45 0.00 0 0
Total 20,279.26 252.71 1.25