Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
28 1,016.75 452.12 44.47  
1 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soakpit Sinking 250mm X 200mm Big dia Tubewell & New UPVC Pipe line and other allied works (PART ¿A) at RASHIKBILL ZONE ¿ I PWSS under Cooch Behar Division, PHED ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000241/2021-2022 890/CD 24/12/2021 120 MATARA CONSTRUCTION CO. 253.04 238.58 94.29 98
2 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soakpit Sinking 250mm X 200mm Big dia Tubewell & New UPVC Pipe line and other allied works (PART ¿A) at RASHIKBILL ZONE ¿ I I PWSS under Cooch Behar Division, PHED ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000242/2021-2022 891/CD 24/12/2021 120 GHOSH AND SAHA CONSTRUCTION 263.46 25.73 9.77 1
3 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC & New laying UPVC Pipe line construction of Sluice valve chamber & other allied works at RASHIKBILL PWSS under Cooch Behar Division, PHED (PART ¿M) ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000251/2021-2022 900/CD 24/12/2021 120 KAJAL KUMAR DE 91.14 88.74 97.37 1
4 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC & Construction of Pillar for Pipeline with driving by Sal-bullah & other allied works at RASHIKBILL PWSS under JAL JEEVAN MISSION PART ¿ M ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000295/2022-2023 896/CD 22/09/2022 30 KAJAL KUMAR DE 3.58 3.45 96.37 1
5 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC & other allied works at RASIKBILL ZII PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000371/2022-2023 1024/CD 29/09/2022 30 KAJAL KUMAR DE 9.98 9.92 99.4 99
6 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC & other allied works at RASIKBILL ZI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000372/2022-2023 1025/CD 29/09/2022 30 MATARA CONSTRUCTION CO. 10.02 9.10 90.82 100
7 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Providing FHTC & other allied works at RASIKBILL ZONE ¿ I PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000416/2022-2023 1226/CD 28/11/2022 60 HIRAK CONSTRUCTION 97.91 59.13 60.39 90
8 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Supply and delivery of 200 mm dia UPVC pipe(CD) for Rasikbill Zone-I 3rd Site Tubewell under Cooch Behar Division , P.H.E Dte. ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000522/2021-2022 1570/CD 23/03/2022 15 MATARA CONSTRUCTION CO. 2.98 2.16 72.48 1
9 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Supply and delivery of 200 mm dia UPVC pipe(CD) for Rasikbill Zone-II 3rd Site Tubewell under Cooch Behar Division , P.H.E Dte. ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000523/2021-2022 1571/CD 23/03/2022 15 GHOSH AND SAHA CONSTRUCTION 2.98 2.98 100 0
10 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Construction of balance portion of inside drain HWS of Rasikbil (Zone-II) WSS under Tufanganj Sub-Division, PHE Dte. ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000548/2021-2022 409/TFG 17/03/2022 15 NABIN DEBNATH 3.29 3.02 91.79 1
11 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation construction of inside drain, pathway chamber with into the HWS of Rasikbill Zone-I PWSS under Tufanganj Sub-Division, PHED ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000570/2021-2022 408/TFG 17/03/2022 15 NABIN DEBNATH 3.88 3.77 97.16 1
12 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation construction of Chamber, balance portion work of Rasikbil Zone-IIPWSS under Tufanganj Sub-Division, PHED. ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000758/2022-2023 84/TFG 27/04/2022 20 NABIN DEBNATH 1.77 1.63 92.09 1
13 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Material Requisition To Resource Division RTOR000017/2021-2022 788/CD 07/12/2021 Resource Division 11.31 0.00 0 0
14 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Material Requisition To Resource Division RTOR000056/2021-2022 1198/CD 01/02/2022 Resource Division 5.87 0.00 0 0
15 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Material Requisition To Resource Division RTOR000104/2023-2024 219/CD 27/04/2023 Resource Division 33.04 0.00 0 0
16 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation fhtc VCH/000112/2022-2023 BP-2022-23-22 13/04/2022 ASHIM KUMAR CHAKRABORTY 0.16 0.00 0 0
17 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation SOIL INVESTIGATION AT BALARAMPUR VCH/000195/2022-2023 BP_104_22_23 21/06/2022 MOYTEC 0.96 0.00 0 0
18 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation OHR AND FHTC AT ANDARAN FULBARI VCH/000206/2022-2023 BP_96_22_23 20/06/2022 GEETA CONSTRUCTION 146.99 0.00 0 0
19 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation SOIL INVESYIGATION VCH/000235/2022-2023 BP_104_22_23 21/06/2022 MOYTEC 1.19 0.00 0 0
20 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation HRING VECHICLE VCH/000418/2022-2023 BP-22-23-141 15/07/2022 AJAD HOSSAIN 0.88 0.00 0 0
21 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation HIRING VEHICLE VCH/000729/2022-2023 266 30/09/2022 SWAPAN KR.SARKAR 0.18 0.00 0 0
22 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation PAYMENT TO RESOUCE DIV VCH/001341/2021-2022 BP-2021-22-400 22/02/2022 EXECUTIVE ENGINEER RESOURCES DIVISION P.H.E.DTE. 40.00 0.00 0 0
23 COOCHBEHAR Coochbehar Division Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation FHTC VCH/001688/2021-2022 BP_2021_22_500 31/03/2022 SANJAY MANDAL 9.84 0.00 0 0
24 COOCHBEHAR Northern Mechanical Division II Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation QUOTATION FOR NEW SERVICE CONNECTION AT RASHIKBIL (AUG) TW NO- I,Z-I BILL/00025/2023-2024 BP-2023-24-18 27/04/2023 WBSEDCL 1.06 0.00 0 0
25 COOCHBEHAR Northern Mechanical Division II Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation QUOTATION FOR NEW SERVICE CONNECTION AT RASIKBIL PWSS (AUG) Z-II,TW NO-I BILL/00026/2023-2024 null 11/04/2023 UJJWAL ROY 1.06 0.00 0 0
26 COOCHBEHAR Northern Mechanical Division II Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation QUOTATION FOR NEW SERVICE CONNECTION AT RASIKBIL PWSS (AUG) Z-II,TW NO-I BILL/00110/2023-2024 BP-2023-24-20 27/04/2023 WBSEDCL 1.06 0.00 0 0
27 COOCHBEHAR Northern Mechanical Division II Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for AUGUMENTATION of RASIKBIL water supply scheme, TW no I of Zone-I and TW ¿I of Zone-II under JJM under NMD-II, PHE Dte. APD. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 3, Cooch-Behar Mechanical Sub-Division, ORD/000053/2023-2024 1134/NMD-II 08/06/2023 30 MADHAB SAHA 18.60 3.91 21.02 100
28 COOCHBEHAR Northern Mechanical Division II Augmentation of Rasikbil piped water supply scheme. , SM/09300 Augmentation Installation of Automatically Controlled Chlorinator (supply departmental) for accurate dosing of chlorine solution at Rampur VI , Santoshpur I & II , Bajejama Chilakhana I, Rasikbill Zone-I P/H No.I under CMSD PHE. Dte. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000932/2020-2021 1289/CMSD 15/03/2021 7 PRAGATI CONSTRUCTION COMPANY 0.52 0.00 0 0
Total 1,016.72 452.11 44.47