Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
20 169.06 4.53 2.68  
1 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting Providing F.H.T.C. & other allied work related to pipe line in the command area at DEOCHARAI PWSS under Cooch Behar Division, PHE Dte. (Part-F) ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000192/2021-2022 204/TFG 07/10/2021 30 SANJAY MANDAL 4.76 4.53 95.17 1
2 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at DEOCHARAI W.S.S under Cooch Behar Division P.H.E.Dte. ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000542/2021-2022 1642/CD 29/03/2022 60 M/S. NITYAGOPAL BANIK 41.30 0.00 0 1
3 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting Providing FHTC & other allied work related to pipeline in the command area at Deocharai PWSS under Cooch behar Division, PHED(Part-A) VCH/000119/2021-2022 null 20/04/2021 M/S. NITYAGOPAL BANIK 8.31 0.00 0 0
4 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting Providing Functional Household tap connection(Unmetered)125 Nos. in Rajpur Piped Water Supply Scheme under Cooch Behar Division, P.H.E Dte. under Jaldhara Programme VCH/000124/2021-2022 null 20/04/2021 MATARA CONSTRUCTION CO. 5.02 0.00 0 0
5 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc deocharai VCH/000545/2021-2022 BP-2021-22-69 27/07/2021 M/S. NITYAGOPAL BANIK 8.31 0.00 0 0
6 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/000693/2021-2022 BP-2021_22_155 20/08/2021 BABA LOKENATH UN EMPLOYED ENGINEERS CO OP SOCIETY LTD 2.46 0.00 0 0
7 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting FHTC AT DEOCHARAI VCH/000734/2022-2023 223 02/09/2022 M/S. NITYAGOPAL BANIK 16.74 0.00 0 0
8 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting PROVIDING FHTC AT DEOCHORAI PWSS ( PART-A) VCH/000758/2021-2022 null 30/09/2021 M/S. NITYAGOPAL BANIK 14.78 0.00 0 0
9 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting PROVIDING FHTC UNDER DEOCHOORAI PWSS PART-D VCH/000766/2021-2022 null 30/09/2021 SANJAY MANDAL 5.05 0.00 0 0
10 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting FHTC AT Deocharai VCH/000955/2021-2022 BP-2021-22-236 28/10/2021 DIGENDRA CH DEY & SONS 10.14 0.00 0 0
11 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/001017/2021-2022 BP-2021-22-202 11/10/2021 SWAPAN KR.SARKAR 0.85 0.00 0 0
12 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting Providing household tap connection of drinking water to the household of command area under Paran Majumder Water Supply Scheme under Mathabhanga Sub Division, P.H.E. Dte. under Jalswapna Prakalpa VCH/001088/2021-2022 BP-2021-22-305 20/11/2021 M/S. NITYAGOPAL BANIK 1.52 0.00 0 0
13 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting cost of meterial VCH/001157/2021-2022 BP-2021-22-318 06/12/2021 EXECUTIVE ENGINEER RESOURCES DIVISION P.H.E.DTE. 2.56 0.00 0 0
14 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting cost of meterial VCH/001163/2021-2022 BP-2021-22-318 06/12/2021 EXECUTIVE ENGINEER RESOURCES DIVISION P.H.E.DTE. 2.25 0.00 0 0
15 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting FHTC AT DEOCHARAI VCH/001329/2020-2021 BP-2021-22-220 11/10/2021 MS SURAJIT MAJUMDER 5.06 0.00 0 0
16 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/001356/2021-2022 BP-2021-22-376 17/02/2022 NABIN DEBNATH 15.37 0.00 0 0
17 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/001379/2021-2022 BP-2021-22-404 24/02/2022 ASHIM KUMAR CHAKRABORTY 4.08 0.00 0 0
18 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/001589/2021-2022 BP-2021_22_409 02/03/2022 NABIN DEBNATH 5.07 0.00 0 0
19 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting fhtc VCH/001611/2021-2022 BP_2021_22_435 10/03/2022 ASHIM KUMAR CHAKRABORTY 11.98 0.00 0 0
20 COOCHBEHAR Coochbehar Division Retrofitting of existing Deocharai Piped Water Suply Scheme to provide FHTC connection to the people of the command area of Deocharai Piped Water Supply Scheme , SM/07162 Retrofitting FHTC SALMARA VCH/001761/2021-2022 BP-2021_22_454 16/03/2022 TAPAN CHANDA 3.45 0.00 0 0
Total 169.09 4.53 2.68